B4063 Gloucester to Cheltenham (G2C) Cycleway scheme - Estcourt Road Roundabout to Elmbridge Court Roundabout

Gloucestershire County Council Published 4 Jul 2023 Contracts Finder

key details

Value£3,500,000
Statusactive
Category (CPV) 45233000 +1 more
Deadline3 Aug 2023
Contract start18 Sept 2023
Contract end3 Jan 2025
SME suitableYes
OCIDocds-b5fd17-f2e2ea4f-fc5b-4e51-a615-cc4cb22e3c93

description

This advert is intended to notify suppliers of the tender for B4063 Gloucester to Cheltenham G2C Cycleway scheme between Estcourt Road Roundabout to Elmbridge Court Roundabout, including Llanthony Road and Pirton Lane junctions.

The site is found to the northeast of Elmbridge Court Roundabout, approx. post code GL3 1AD, with two individual junctions, Llanthony Road, approx. post code GL2 5JQ, and Pirton Lane, approx. post code GL3 1AE. This is part of a bigger scheme to address the needs of pedestrians and cyclists and create an Active Travel corridor between the towns of Cheltenham and Gloucester. The overall scheme will implement a continuous cycleway for cyclists of all ages and abilities between the main hubs of Cheltenham and Gloucester, utilising London Road, Cheltenham Road, B4063, and part of the A40 between Arle Court roundabout and Benhall roundabout.

This contract is looking for a Principal Contractor to deliver the construction phase of Estcourt Road Roundabout to Elmbridge Court Roundabout, including Llanthony Road and Pirton Lane junctions.

A more detailed summary of the works is included below:

Construction Phase key Deliverables are as follows:

Provide suitable Traffic Management during the construction works.

Pedestrian access to residents always during the construction works.

Utility diversion works, being arranged by GCC for PC to liaise and accommodate.

New drainage works and tie-in to existing.

A mixture of Highway, segregated footway and cycleway track and new shared use path construction.

Remove existing and install new kerbs to match new alignment.

Junction realignments.

Carriageway surfacing repairs and reprofiling.

New traffic signals facilities across the route.

A summary of the outline programme for the scheme is shown below:

Tender start: Monday 3rd July 2023

Tender return: Thurs 3rd August 2023

Award: Monday 4th September 2023

Anticipated Works Start Date: Monday 9th October 2023

Completion: Friday 3rd January 2025

Overall Duration: 62 weeks

Indicative Value: GBP3.5m

The proposed procurement route will be a single stage Open Procedure using the NEC4 ECC form of Contract, Option A Priced Contract with Activity Schedule.

Full details will be available in the tender pack that we intend to advertise on Monday 3rd July 2023.

The Market Information Event for Estcourt Road Roundabout to Elmbridge Court Roundabout will be undertaken on 9 to 9.50am Wednesday 12th July 2023 via Microsoft Teams.

Please send a message using the messages function of the Procontract advert if you would like to attend.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
4 Jul 2023 Tender (tender) · ce2359f9-74fd-437a-9fac-2717b27c881b-659295

more from Gloucestershire County Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.