GB-Edinburgh: REFURBISHMENT AND UPGRADE OF AILSA CRAIG LIGHTHOUSE

Northern Lighthouse Board Published 21 May 2024 Contracts Finder

key details

Value£204,561
Statuscomplete
Category (CPV) 45442121 +6 more
RegionScotland
Deadline16 May 2024
Contract start31 May 2024
Contract end28 Feb 2025
SME suitableNo
OCIDocds-b5fd17-a85c522a-ddfc-49b0-a318-088be0a3087e

Award

SupplierValueDateStatus
TRAC HLM Ltd £204,561 16 May 2024 active

description

Painting work. Painting work of buildings. Painting and protective-coating work of structures. Painting work of structures. Concrete. Woodwork. Painting and glazing work. Ailsa Craig Lighthouse is located on Ailsa Craig, an island in the Firth of Clyde, just offshore from Girvan, South Ayrshire at Latitude 55° 15.126'N, Longitude 005° 06.523'W. The lighthouse was established in 1886 to mark the west side of the main entrance into the Clyde. Designed by David Alan Stevenson and constructed by Hill and Son of Leith, the painted white stone tower stands 11 metres high at an elevation of 18 metres above sea level. The existing optic has a range of 17 nautical miles with a flashing white character (1) every 4 seconds.

The Lighthouse station consists of a tower, engine room, control room, battery room, store room and domestic accommodation. The former lightkeeper's houses and all other buildings are privately owned.

The main items of project work are as listed below:-

1.Carry out a full Asbestos Refurbishment / Demolition Survey on all NLB operational buildings prior to the commencement of any work. The survey, sample collection and sample analysis must be carried by a UKAS accredited contractor in accordance with ISO 17020, ISO 17025 and Health and Safety Executive Guidance Notes; HSG 248, Asbestos: The analysts' guide for sampling, analysis and clearance procedures" and HSG264, Asbestos: The survey guide.

2.The Principal Contractor is expected to test the existing 'HCL' fall arrest system and re-certify it if necessary before use. The Principal Contractor is to provide the Project Leader with all relevant test certification for record and audit purposes.

3.Deliver all plant, tools, materials, etc to NLB Oban packaged for helicopter under-slinging.

4.Land plant, tools, materials, etc on site and establish welfare facilities.

5.Carry out minor civil works and full redecoration of the lighthouse station.

Tender issue: 8 March 2024

Mandatory Pre-tender site visit: 5 April 2024 (TBC)

Tender return date: 18 April 2024

Latest date contract to be awarded to successful contractor: Est. 3 May 2024 Materials, plant, etc. to be delivered to NLB Oban depot: 31 May 2024 Materials, plant, etc. to be landed on site by ship / helicopter: 11 June 2024 Site clearance / de-mobilisation: 26 October 2024

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

3 notices published against this procurement.

PublishedTypeRegimeNotice
8 Mar 2024 Tender (tender) · 2a6317c7-30c3-422a-8f77-0ded5f079d0d-730324
5 Apr 2024 Tender amendment (tenderAmendment) · 2a6317c7-30c3-422a-8f77-0ded5f079d0d-738157
21 May 2024 Award (award) · 70fd2fab-715b-47d9-9496-070c0a62a5d7-752904

more from Northern Lighthouse Board

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.