gvtcx

Refurbishment of Leeds Media Centre

UNITY PROPERTY SERVICES LIMITED Published 21 Nov 2020 Contracts Finder

key details

Value£1,500,000
Statusactive
Category (CPV) 45000000
Deadline18 Dec 2020
Contract start1 Apr 2021
Contract end31 Mar 2022
Proceduredirect
SME suitableYes
OCIDocds-b5fd17-d553b7c8-cabf-470a-b8db-9e0bd4daf7b8

description

Unity Property Services Limited (Unity) has partnered with Leeds City Council to design and deliver a significant regeneration project, namely the refurbishment of the Leeds Media Centre at 21 Savile Mount, Chapeltown, Leeds, LS7 3HZ. The project will be part funded by the European Regional Development Fund (ERDF).

Unity wishes to procure a single Contractor to carry out alteration and refurbishment works to the existing Media Centre. The building comprises a three storey flat roofed block with a basement, originally constructed in 1921 and significantly modified since. The last major refurbishment of the building took place in 2001.

  1. Scope of Works

The project comprises work on the existing building as generally shown on Nicol Thomas Architects elevations and floor plans drawings M4568.P.02, M4568.S.01 and M4568.P.01 and as further described in Nicol Thomas Architects Outline Schedule of Repair/Refurbishment Works Statement and Construction Cost Estimate dated March 2020, including:

Removal of existing redundant plant from the roof, recovering the roof with a tapered insulation system
Renewal of existing rainwater goods
Removal and replacement of existing external building envelope components including windows and doors
Repairs to the external building envelope
Internal layout reconfiguration
Repair, replacement and redecoration to internal areas
Renewal of all sanitary fittings
Renewal of the kitchen facilities to first and second floors
Replacing the existing heating system
Replacing the existing ventilation system
Replacing the existing passenger list
Alterations to existing building services installations including installation of some new ducted mechanical ventilation
Works required under the BREEAM refurbishment category including the provision for renewable energy solutions.

The drawings referred to above are attached as Appendix XX

The scope of work for the refurbishment of the Media Centre has been prepared on the basis of the designs prepared by Nicol Thomas. The estimated cost for building works based on this design is £1,522,000 including an allowance for professional design fees incurred as part of the design and build package but excluding VAT.

The project is to achieve an assessment rating of 'Very Good' against BREEAM Non-Domestic Refurbishment and Fit-Out 2014, parts 2,3 and 4. T

Additional information: Following a request for clarification regarding the page limits for Part 4 Scored Question 5 - Health & Safety. We would advise bidders to note that the question asks for 5 Risk assessment to be included as part of the response. The 5 Risk assessments can be included as attachments to your response and will not be counted towards the specified page limit of 4 pages of A4. The Method Statement will be counted as part of the page limit.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
9 Dec 2020 Tender amendment (tenderAmendment) · 99d30a5b-57d0-452f-a02a-c1b4673ac596-399334

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.