EKFB Princess Risborough to Aylesbury (PRA) Overbridge Pier Cladding and Finishing
key details
| Value | £2,500,000 |
|---|---|
| Status | active |
| Category (CPV) | 45262650 +1 more |
| Region | East Midlands, West Midlands, South East |
| Deadline | 18 Oct 2023 |
| Contract start | 30 Mar 2024 |
| Contract end | 27 Dec 2024 |
| SME suitable | Yes |
| OCID | ocds-b5fd17-a52103e7-7e45-45b9-bb1b-8b33f5e1bbce |
description
Title
Cladding and Sprayed Concrete
Design and planning of the works before physical works commence.
The Subcontractor is required to support the Contractor during the planning phase to ensure an optimum design and delivery of the asset.
To deliver the above the Subcontractor will, at least:
| - | Attend weekly progress meetings, and actively engage providing ideas and solutions. |
| - | Provide constructibility report for the works. |
| - | Provide programme for the works. Special attention to those elements that require long lead in i.e., procurement of pre-cast elements moulds, and therefore require early procurement/instructions. |
For the Construction of the works
The Subcontract Works includes for the provision of all management, labour, materials, plant and equipment, supervision, and other resources necessary and ancillary to safely complete the construction and handover of cladding of the PRA OB pier piles, as described in the specifications, drawings, HS2 standards and other documents provided:
Pier Cladding Update- Performance Criteria
Options
Precast concrete 160 mm to 200mm thick discussed.
Steel sections bracketed to pile.
GRP sections fixed to outside of pile with compressible liner/ infill.
Formwork with pile wrapping and RC wrapping mesh/ rebar.
Design Criteria for finisher pier cladding.
Pier cladding noted on drawings 3200mm precast cladding 200 mm thick.
Maximum outside diameter = 3200mm.
Minimum inside diameter = 2800mm.
Arrangement allows for overall out of position of installed pile of 100mm maximum. Assuming 2600mm Dia pile cap.
Corbel support from pile designed to support self-weight of pier cladding.
Cladding to be isolated from pier architectural non-participating with respect to capacity of pile.
Differential movement to be allowed of minimum 10mm if fully infilled or grouted.
Potential to leave unfilled and sealed from water ingress at top.
Options for applying Cladding to uneven concrete pile.
Potential to use Steel shell.
Potential to use GRP cladding.
Height of Cladded Pile approximately 5m
Max SW cladding = 225 high density (25kN/m3 ) thick casing .
Shell with compressible layer/ foam infill to ensure non-structural.
Allowance has been made for grout infill if necessary but compressible layer required to isolate cladding from load effects.
Additional information: Currently No Specification - Supply Chain involvement in the Design required
documents
- https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=74459723 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/6e7c674e-8286-4c4b-9f2e-44168bd95329 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 5 Oct 2023 | Tender (tender) | · | 6e7c674e-8286-4c4b-9f2e-44168bd95329-686341 |
more from Eiffage Kier JV HS2 Main Civils Works, Lots C2 & C3
- EKFB JV - Precast Concrete UTX (Under Track Crossing) chambers system and adjoining duct works · £500,000 · 23 Jun 2026
- EKFB JV - NC2A Footway and Accommodation Overbridges FRC works · £2,500,000 · 11 Jun 2026
- EKFB JV - Ancillary Culverts Works package NC2A · £1,000,000 · 18 May 2026
- EKFB JV - Highways Works - NC2A draft · £5,000,000 · 28 Apr 2026
- EKFB JV - Highways Works - NC2A · £5,000,000 · 28 Apr 2026
- Noise Barrier Specialist Bolts and Fixings · £5,000,000 · 18 Mar 2026
- EKFB JV - Seeding Works - G2S · £10,000,000 · 11 Feb 2026
- EKFB JV - Planting Works - G2S · £5,000,000 · 11 Feb 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- DEV/R005 - Colonsay View, Edinburgh Cladding Works · Hillcrest · £2,115,000
- Phase 1 Cladding Remedial Works Project - French, Finch and Margaret House · Wandle Housing Association Limited · £2,716,458
- CBC-1212-FC-SK - Construction Lot 2 Priory View Cladding Project - AWARD · Central Bedfordshire Council · £1,833,705
- Pillfold House EWS Cladding Remediation Works · WANDLE HOUSING ASSOCIATION LIMITED · £204,624,268
- MWF Lot 3 - Butts Primary School - Thermal Upgrade - AWARD · Hampshire County Council
- Five Acres Primary School Roof Works · Oxfordshire County Council
- MWF Lot 3 DA - Horndean Technology College - SCOLA Reclad - S Block - AWARD · Hampshire County Council
- 19380 - BALMOOR UNIT 1 - CLADDING WORKS - PETERHEAD · Aberdeenshire Council · £97,550
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.