Quantitative Schedule Risk Analysis (QSRA) on Net Zero Buildings - Domestic (NZB -D ) Grant Applications

BEIS Published 23 Aug 2023 Contracts Finder
The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£864,000
Statuscomplete
Category (CPV) 73000000
Deadline26 May 2023
Contract start14 Jul 2023
Contract end10 Jul 2026
Procedureselective
SME suitableYes
OCIDocds-b5fd17-253e8ef6-6721-48d5-aae0-7dc3e1c5d75a

Award

SupplierValueDateStatus
DELOITTE LLP £864,000 26 Jul 2023 active

description

***** THIS IS AN AWARD NOTICE, NOT A CALL FOR COMPETITION *****

This procurement is being concluded following a mini competition under the Crown Commercial Services - RM6126 - Research & Insights DPS

This procurement is being concluded following a competitive procurement exercise.

Brief Description of Requirement

The contract is to carry out two Quantitative Schedule Risk Assessment (QSRA) on the applications received under HUG 2 and SHDF schemes.

The analysis will be on applications received under each scheme; HUG 2 have approved 45 projects; SHDF Wave 2.1 expects to fund c.107 projects.

The aim is to ensure delivery of QSRA by an appropriate contractor to provide a cumulative distribution function of the delivery timetable for HUG 2 and SHDF Wave 2.1.

Specifically the QSRAs are expected to provide probabilistic date ranges (e.g., P10, P50, P80 along with associated confidence intervals) for the completion of the HUG 2 and SHDF Wave 2.1 schemes. Delivery stage based on key milestone dates provided by Grant Recipients, alongside (where available) previous Grant Recipient performance data and wider information available that relate to grant allocated retrofit schemes.

The two QSRAs are required to be completed within 6 weeks of the contract start date.

The maximum budget allocated for each QSRA is £144,000.00 (excl VAT). The total contract budget for the three year period to conduct QSRA is £864,000.00 (excl. VAT). The authority will assess their need for exercising the extension option on an annual basis

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
23 Aug 2023 Award (award) · ca105523-1c26-489e-a16b-81e0e88d2d5a-674460

more from BEIS

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.