Tiptree Parish Council: Rebuild (including silt removal) of Duck Pond
key details
| Value | £250,000 |
|---|---|
| Status | complete |
| Category (CPV) | 45300000 +2 more |
| Deadline | 8 Jul 2022 |
| Contract start | 1 Aug 2022 |
| Contract end | 30 Sept 2022 |
| Procedure | limited |
| SME suitable | Yes |
| OCID | ocds-b5fd17-2437a9fd-ed59-495a-9e88-fd0fa7651f79 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| The A.G.A. group Limited | £81,309 | 2 Aug 2022 | active |
description
Re-Build (including draining and silt removal) of Grove Lake Duck Pond - Specifically, the repair of the walkways (root damage), the walls of the lake where brickwork is failing, the removal of silt from the lake (approx cubic 290m), delivery of SILT trap for two x inlets.
Detailed work as follows:
Work Schedule: - Silt Removal:
Silt in Pond - approx. 290 cube
- Cofferdams to be set up splitting the pond into 3 or 4 areas
- Inlets and outlet to be diverted where required
- Silt allowed to drain and then removed from Pond
- Silt to be stored and dried next to pond then taken away from site
- Disposal of silt as recommended by local authority (The Council may have a location to remove the silt too, via a local farmer and the Council's allotments, but this is not guaranteed).
Work Schedule - Walkway:
- The concrete walkway above the brick walls is no longer even, and provides a trip hazard for walkers. It has been repaired with Tarmac in order to get the differing levels to "meet", but now requires re-setting to ensure an even walkway around the entire pond.
Work Schedule - Wall Damage:
- As the damage to the walls is only visual above the water line a further inspection would be required when each section is drained
- All existing brickwork to be jet washed for closer inspection
- Any failing brickwork to be replaced
- Any lose mortar to be replaced between brickwork
- The movement in the walls will make future guarantees limited on any works undertaken
Note: The pond is not leaking, and the base of the pond is estimated to be a proportion of cement, and a proportion of clay (the surrounding area is made up of London Clay)
Work Schedule - Island:
- An inspection is required below water line of the brickwork
- Some copings to be re-laid or replaced as necessary
Work Schedule - Introduction of Aquatic Planting:
- It would be possible to introduce some planting zones, but these would be required to be separated from the fish
- Shallow marginals or floating planters could be introduced
- Plants provide a balanced aquatic eco-system and would help keep the phosphate levels lower
Work Schedule: Inlets and outlets
- The outlet could be modified to allow for greater collection of silt and floating debris, this could help alleviate any future flooding of the road
- The inlet from the feeder SuDS pond requires a silt trap, as currently it appears as an open pipe
documents
- https://www.contractsfinder.service.gov.uk/Notice/6b850753-8d5e-49d5-be47-507a2b6dfabc , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/5296cbe3-d4c4-41c4-a3e8-00caa17634dd , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 8 Sept 2022 | Award (award) | · | c0ae60eb-673f-4a21-ac4a-a4622cf4d4e9-569933 |
more from Tiptree Parish Council
- Grove Park Playing Field new equipment · £75,000 · 20 Jul 2023
- Community Centre Solar Power · £28,000 · 8 Sept 2022
- WetPour Replacement · £35,000 · 16 Nov 2021
- New Parish offices · £20,000 · 24 Aug 2020
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- 12 Kirby Road; Phase 2 - Internal conversion and fit-out of guesthouse to two 4-bedroom maisonettes. £15k - £400k BHC Building and Refurbishment Framework · Blackpool Council · £217,507
- Lincoln College Loft Insulation - Abbey Building, Friary Building and Temple Building · Lincoln College Group
- Refurbishment Works Lot 3 Blandford Fire Station · Dorset & Wiltshire Fire and Rescue Authority · £878,102
- Domestic Energy Retrofit Works - FAT Notice · Cheshire East Borough Council · £207,500,000
- PP-10183b Hornchurch Academy Trust Construction, Infrastructure, Building Works, Installations and Renewables Open Framework · HORNCHURCH ACADEMY TRUST · £830,000,000
- Barnet Homes Aids and Adaptations Works Contract · Barnet Homes Ltd · £4,000,000
- Replacement and Upgrade of Kitchens 2026 - 2031 · Bolsover District Council · £2,700,000
- Communal Ground Source Heat Pump solution for Gallowhill Multi Storey · Renfrewshire Council · £5,146,851
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.