WP1150 - Survey & Design - Tunnel Vent Vans & Fan Drives

Costain Limited (H7-Heathrow) Published 2 Jun 2026 Contracts Finder

key details

Value£5,000,000
Statusactive
Category (CPV) 71320000
RegionLondon
Deadline9 Jun 2026
Contract start7 Aug 2026
Contract end1 Dec 2026
SME suitableYes
OCIDocds-b5fd17-25f831be-e278-45de-ba56-42465ff8de0f

description

Expression of Interest Tunnel Vent, Fans and Fan Drives MEP Subcontractor

Tunnel Vent, Fans and Fan Drives (Survey and RIBA 4) Scope

The objective of this scope is to replace components that form part of the ventilation system at Central Terminal Area (CTA) North and South, Terminal 4 North and South and Sipson Farm, that are at their end of life. The components of concern are Fan Drives and Low Voltage Air Circuit Breakers.

It is proposed that all components for the 8 No. existing Variable Speed Drives (VSD) which are close to their designed lifetime are to be replaced, together with the panel.

It is proposed that all components for the 5 No. existing Direct On-Line (DOL) starters which are close to their designed lifetime are to be replaced, together with the panel are replaced with VSD's.

The VSDs are to be connected to the Tunnel Control System (TCS).

The incoming air circuit breakers (ACB's) and the low voltage protection devices (MCCB/MCB's) within the existing switch gear will be replaced with new devices. Where the impact is significant, this may lead to replacing the entire LV switchgear and the DOL panels for the associated equipment.

New lighting will be provided by energy-efficient LED luminaires, as the existing lighting system is in poor condition.

As part of small power provision, 240V socket outlet assemblies shall be provided near damper units. The existing junction boxes and cable termination boxes need to be replaced with new equipment.

ItemQuestion
Q1What capability do you have of understanding the requirements for replacing Electrical infrastructure etc., Specifically considering the constraints of an operational rail network?
Q2What capability do you have of carrying out a survey of the 5 ventilation buildings non-operational hours to provide all the information required to complete the RIBA 4 design?

Note: - RIBA 5 onwards including construction is excluded.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
2 Jun 2026 Tender (tender) · 30b4b20a-4bc7-4af3-a070-34305c20e5bb-900111

more from Costain Limited (H7-Heathrow)

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.