GB-Edinburgh: Refurbishment and Upgrade of Sumburgh Head Lighthouse

Northern Lighthouse Board Published 11 Sept 2023 Contracts Finder

key details

Value£220,150
Statuscomplete
Category (CPV) 45310000 +3 more
RegionScotland
Deadline6 Sept 2023
Contract start18 Sept 2023
Contract end29 Feb 2024
Procedureopen
SME suitableYes
OCIDocds-b5fd17-24d5d4bc-8304-4b6a-a62d-a2c48832e02a

Award

SupplierValueDateStatus
RS Merriman Limited £220,150 6 Sept 2023 active

description

Refurbishment and Upgrade of Sumburgh Head Lighthouse

The main items of project work are as listed below:-

DGPS Removal.

Sumburgh Head is one of the Northern Lighthouse Boards (NLB), Dynamic Global Positioning System (DGPS) stations. This system has now been discontinued and therefore all items and infrastructure relating to DGPS must be taken down/demolished and removed from site. This includes :

•2no. 18m High LTF Towers, as shown on archive drawing 080115(C)

•Concrete bases for each of the towers.

•GRP Feeder house and concrete base.

•Timber stockade fence around feeder house.

•Aluminium flagpole arrangement forming farady cage at feeder house - see Drg C-SUM-19 •Lister Engine housed in existing control room.

•External Fuel Tank

All the above items can be viewed during the proposed contactors site visit.

Installation on new bearing ring for Optic Lantern.

The current First Order Fresnel Lens is rotated on a float and mercury bath. With the health hazards relating to mercury vapour, this system is to be replaced by a mechanical, motor driven bearing ring.

The manufacture and installation of this system, including the mercury removal, is being carried out by Amon Electronics, based in Northern Ireland. The successful tenderer for this project shall take on Amon Electronic as a nominated sub-contractor and they will be expected to coordinate and supervise the installation work, keeping open a direct line of communication throughout.

For detailed description of the works refer to the Bill of Quantities.

Site Visit

A site visit is planned for 31 July 2023. Date to be confirmed. This is a mandatory requirement and any supplier not attending the site visit will be excluded from this tender exercise. All Tenders should submit a request to attend via the tenderbox message centre to confirm attendance and names of representatives attending site.

Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
7 Jun 2023 Tender (tender) · 208804d3-e979-4bc9-a936-f96fdf2be850-651365
11 Sept 2023 Award (award) · 4d72c218-0eac-4ff2-9dd4-e9f613fbfdf0-679452

more from Northern Lighthouse Board

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.