Westbrook Weir Modelling and Outline Design
key details
| Value | £81,663 |
|---|---|
| Status | complete |
| Category (CPV) | 90700000 |
| Region | South East |
| Deadline | 12 Sept 2025 |
| Contract start | 6 Oct 2025 |
| Contract end | 30 Mar 2026 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-21f10dcc-277e-4012-91bc-2fa8fb0af6e3 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| WSP UK Limited | £81,663 | 5 Oct 2025 | active |
description
The Environment Agency is seeking to appoint a Contractor to undertake flood risk modelling and outline designs relating to Westbrook Mill weir on the River Wey (SU9666944205) and its proposed removal.
Site Background
Westbrook mill has been present for approximately 300 years, and numerous weirs and control structures have been in place maintaining a head of water for its operation. The mill and associated factory have been closed for decades and there is negligible heritage value associated with the site. The weir at Westbrook Mill consists of six 1.5m wide sluice gates in steel frames. There is a difference of
1.3m between the upstream and downstream bed levels, and a maintained upstream water level 1.6m above the weir sill of 36.3m AOD. The side walls downstream of the weir are cast concrete and there is a cast concrete central pier which extends 15m downstream under the road bridge giving access to the complex car park. An access walkway is present over the weir, and the weir is manually operated. The cast concrete 'troughs' formed by the walls and the central island also have a cast concrete bed slab set at approximately 36.2m AOD which functions as a second, shallow weir at low water level conditions.
Upstream of the weir the channel is confined between steel sheet pile walls with concrete capping beams for approximately 50m.
There are three overspill weirs upstream that feed the Hell Ditch (SU9582944564, SU9630344350, SU9655644244), which rejoins the main river approximately 3km downstream. There is also an informal breach which introduces additional flow into the Hell Ditch (roughly SU9649544320). In 2016, the Environment Agency installed a brush-furnished fish pass at the most-upstream overspill weir, allowing the Hell Ditch to function as a fish migration route bypassing Catteshall and Westbrook weirs on the main River Wey.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 6 Oct 2025 | Award (award) | · | 3b38e84b-a298-417e-88ee-33a5a62ef3b9-866989 |
more from Environment Agency
- KSL - Nav - East Farleigh Asset Refurbishment · £7,490,000 · 28 Jul 2026
- EAN - AOMR - East & National Eel Pass Programme · £4,791,694 · 28 Jul 2026
- NW - AOMR - Lot 2 25-27 GMMC MEICA D&B Package · £1,200,000 · 28 Jul 2026
- YOR - CDF - Tidal Ouse Left Bank Saltmarshe - SOC-OBC (ESE) · £64,282 · 28 Jul 2026
- YNE- Stokesley- MMF direct award- 26-27 FY · £74,739 · 28 Jul 2026
- YNE AOMR Lot 1 Asset Recon Skerne South Park Fish Pass Renovation · £46,798 · 27 Jul 2026
- WMD-PFR-Barton to New Holland Lot 2 · 3 Jul 2026
- YOR - CDF - Tidal Ouse Left Bank Saltmarshe - SOC-OBC (PD Contract) · £19,716 · 3 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- The Provision of Ecology Services · Loughborough University
- Provision of Wastewater Quality Testing Service · Armagh, Banbridge & Craigavon Borough Council
- Biodiversity Net Gain (BNG) · NORTHUMBRIAN WATER LIMITED · £5,700,000
- SAMM (Strategic Access Management & Monitoring) for the Wealden Heaths Phase II Special Protection Area (SPA) · East Hampshire District Council · £432,000
- Production of seabird flight height distributions from at-sea laser rangefinder data · JNCC SUPPORT CO · £28,000
- Strategic Flood Risk Assessment and Water Cycle Study · Borough Council of Kings Lynn and West Norfolk
- Tender for the appointment of a consultant on behalf of the Wye Nutrient Management Board to review the Wye Catchment Management Plan 2019 and develop a new Wye Catchment Management Plan 2025 · Herefordshire Council
- Procurement for National River Flow Archive Peak Flows Dataset Maintenance · ENVIRONMENT AGENCY · £0
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.