gvtcx

M5 Junction 10 Improvements Scheme

Gloucestershire County Council Published 18 Jul 2023 Contracts Finder

key details

Value£200,000,000
Statuscomplete
Category (CPV) 45000000
Deadline16 Sept 2022
Contract start16 Jun 2023
Contract end31 Dec 2027
Procedureselective
SME suitableNo
OCIDocds-b5fd17-f08c50bc-621c-4a66-82c8-3a3fe51271ad

Award

SupplierValueDateStatus
Galliford Try Construction Limited £200,000,000 14 Jun 2023 active

description

Background

Gloucestershire faces significant challenges to achieve its vision for economic growth. A

Joint Core Strategy (JCS) - a partnership between Gloucester City Council, Cheltenham

Borough Council and Tewkesbury Borough Council was formed to produce a co-ordinated

strategic development plan to show how the region will develop during the period up to

2031. This includes a shared spatial vision targeting 35,175 new homes and 39,500 new jobs

by 2031. Major development of new housing (c.9,000 homes) and employment land

(c.100ha) is proposed in strategic and safeguarded allocations in the West and North West

of Cheltenham, much of which lies within Tewkesbury Borough Council. This, in turn, is

linked to wider economic investment, including a government supported and nationally

significant Cyber Park adjacent to GCHQ, predicted to generate c.7,000 jobs.

The M5 J10 improvement scheme (Scheme or Project) is critical to achieving the vision set

out above. The Scheme was also identified by Highways England in the Birmingham to Exeter

Route Strategy as being critical to: (a) maintaining the safe and efficient operation of the M5

corridor; and (b) enabling the planned development and economic growth around Cheltenham, Gloucester and Tewkesbury.

A Business Case for the Scheme was submitted in March 2019 to the Housing Infrastructure

Fund, wherein the investment case was made. Funding was awarded successfully by HIF in

March 2020.

Further general information regarding background to the Scheme and its current status in

the project lifecycle can be found at the following web link:-

www.gloucestershire.gov.uk/J10

Scheme Objectives

  • Support economic growth and facilitate growth in jobs and housing by providing improved

transport network connections in west and north-west Cheltenham.

  • Provide the transport connections and network capacity in west and north-west

Cheltenham to facilitate the delivery of housing and economic development sites allocated

or safeguarded in the Joint Core Strategy.

  • Provide a transport network in the west and north-west Cheltenham area with the levels of

service, safety and accessibility to meet current and future needs.

  • Deliver a package of measures which is in keeping with the local environment , minimises

any adverse environmental impacts and meets GCC's ambition on sustainable growth,

decarbonisation and net bio-diversity net gain.

  • Provide greater connectivity between Highways England's Strategic Road Network (M5)

and the transport network in west and north-west Cheltenham.

  • Provide a more integrated transport network by providing opportunities to switch to more

sustainable transport modes within and to west, north-west and central Cheltenham.

The Authority is conducting the procurement using the restricted procedure in accordance with the requirements of the Public Contracts Regulations 2015 (SI 2015/102) (PCR 2015) for the purpose of procuring the services and works described

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
18 Jul 2023 Award (award) · 1f473b87-d9ff-47ad-acc7-b5e70d4efa2e-663582

more from Gloucestershire County Council

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.