Temporary Electrics, Water and Site Services (WP39.1) - Old Oak Common (S4) Station - HS2
key details
| Value | £1,000,000 |
|---|---|
| Status | active |
| Category (CPV) | 39370000 +6 more |
| Region | London |
| Deadline | 11 Aug 2021 |
| Contract start | 19 Jan 2022 |
| Contract end | 30 Nov 2029 |
| SME suitable | Yes |
| OCID | ocds-b5fd17-e82f6a25-1d15-4791-ba64-57df83defbef |
description
Temporary Electrics, Water and Site Services
WP39.1 scope consists of the design, supply, installation and site testing of all additional temporary electrics, water and other site services required during the constructions of the whole project which includes HS2 and GWML stations plus Shared Accommodation Building (SAB) at Old Oak Common Station.
All works to be as required during the construction and commissioning and comply fully with the Standards and Guidance documents, as identified in its section 5. Particularly HS2 standards and British Standards 7671:2018 and 7430 2011.
Scope of works will include:-
| • | Relocation of HV Transformers, Main Distribution Units (MDUs) and HV Cabling |
| • | Control of switching for HV supplies |
| • | Relocation of LV MDUs and cabling |
| • | Installation of temporary lighting |
| • | Relocation and supply of additional Road lighting |
| • | Relocation and supply of additional 110V Transformers, cabling, and socket boxes |
| • | Modify existing, supply and Installation of new MDUs |
| • | Modification of existing, supply and Installation of new vehicle changing units |
| • | Re-cabling tower cranes and plant power supplies and lightning suppression units as they are moved to suit the project programme |
| • | Progressive removal of electrical installation at completion of the project |
| • | Installation of additional vehicle and plant changing points |
| • | Periodic electrical testing for BS7671 and PAT requirements |
| • | Relocation, adjustment, and additional site 200mm and 80mm water mains, including values, chambers, and meters |
| • | Relocation of Hydrant mains and Hydrants |
| • | Modifications to site over pumping and power supplies |
| • | Additional temporary fire mains within the construction project |
| • | Installation of standpipes |
| • | Disinfection of water pipework |
| • | Modifications to site WIFI systems |
| • | Modifications to site wide BMS electric and Water meter connections |
| • | Changes to the site drainage systems |
| • | Maintain and relocation of site ventilation system |
| • | Relocation and powering of wheel wash and weight bridge |
The subcontractor is to develop designs to include the installation processes, commissioning, testing and maintain a detailed set of drawings plus operation and maintenance manuals for the temporary installation.
Liaison with BBVS, WSP (main designers) and other Subcontractors will be required in the all works area.
Contract will be NEC3 ECC Option E
About the buyer's selection process:
Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.
The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.
What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: HSEQ, Commercial, Programme, Methodology (particularly with working in a track environment).
Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.
The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.
What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: Commercial, Programme, Methodology, HSEQ, Capability and Capacity.
In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Interchange at Old Oak Common.
No Documentation is included at this point.
Additional information: No Documentation is included at this point.
documents
- https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=56994259 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/9955e95b-280a-4ba3-b776-91e31e444ddd , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 26 Jul 2021 | Tender (tender) | · | 9955e95b-280a-4ba3-b776-91e31e444ddd-454805 |
more from Balfour Beatty VINCI Systra JV
- WP15.03 Old Oak Common Lane (OOCL) - Highways (incl. Utilities) & IEP Depot Temp. / Permanent Road & Retaining Wall (S4) · £20,000,000 · 28 May 2026
- Traffic Management - Old Oak Common (S4) Station · £2,500,000 · 10 Mar 2026
- Fit Out - WP12.10 Statutory and Wayshowing Signage- Old Oak Common (S4) Station · £500,000 · 31 Oct 2025
- WP15 Final Highways Scope - Old Oak Common (S4) Station · £20,000,000 · 21 Aug 2025
- Labour Supply - Old Oak Common (S4) Station · £1,000,000 · 28 Jul 2025
- BBVS & HS2 Station Furniture - HS2 Phase 1 Stations - Old Oak Common (S4) Station · £5,000,000 · 13 May 2025
- WP15.04 IEP Access and Retaining Wall - Old Oak Common (S4) Station · £5,000,000 · 10 Apr 2025
- Fit Out - Primary Steel Framework, Steel Sub Frames, Cladding Track, Firestops, Insulation, Retail Doors and Glazing -WP12.4.1 - Old Oak Common (S4) Station · £10,000,000 · 7 Feb 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Drainage/Watercourses · West Lancashire Borough Council · £50,000
- STDC-PROC-0587 - Hinterland Temporary Drainage Channel · TEES VALLEY COMBINED AUTHORITY · £150,000
- Pressurisation Equipment and Auxiliary Systems Serving Potable, Chilled & Low Temperature Hot Water Services · University of Salford
- Water and Wastewater Services · Barnsley Metropolitan Borough Council · £1,796,750
- Water, Wastewater and Ancillary Services · National Highways · £400,000
- Award of South Uist Drainage – Maintenance Contract 2025/26 · Scottish Government · £53,019
- PL0218 Fairfield Centre Extension - WCC 00002463 · Worcestershire County Council · £682,030
- Payment contribution for replacement of a crane with a new pump store · Met Office · £108,333
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.