Safe and Warm Upgrade Scheme Park View Barlborough - AWARD
key details
| Status | complete |
|---|---|
| Category (CPV) | 45453100 |
| Deadline | 1 Jul 2019 |
| Contract start | 1 Aug 2019 |
| Contract end | 31 Oct 2019 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-d6edb851-fa2e-4633-aa58-a31bd8d9c672 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Matthews and Tannert Ltd | £151,133 | 5 Aug 2020 | active |
description
Bolsover District Council wishes to appoint a principal contractor on the basis of a minor works JCT contract for the undertaking of Safe & Warm upgrade works at the 19 Nr. bungalows and one communal area in Barlborough.
The main scope of this scheme is to provide central heating upgrading, wet room conversion and improved fire safety measures within each of the bungalows. The communal area is only having the heating upgrade works.
Currently, heating and hot water is supplied to each bungalow on a communal system provided from a central boiler house, located on the site. Due to the age and general condition of the boiler it is proposed for each bungalow to have its own independently controlled heating system installed in the form of a gas combi-boiler. The appointed contractor will be charged with the isolation and capping-off of the existing heating system at each bungalow within the programme of works.
Please note that the de-commissioning of the boiler house will not form part of this project and is to be undertaken by the authority's facilities management contractor.
Existing shower areas are to be altered and a full wetroom conversion is to be undertaken to standard designs across all bungalows. This will involve the installation of a new shower, wash hand basin and w/c complete to improve and standardise the facility for all bungalows.
To improve the fire safety aspects of the dwelling the installation of a new multi-sensor alarm system is to be installed and fire-stopping implemented throughout as per the requested fire compartmentation survey which the appointed contractor is to arrange and oversee as part of the project.
It is estimated that a start on site is achievable during August 2019 and that completion of the scheme should be achieved within a 12 week programme.
The tenant needs and requirements are paramount to the successful completion of this project. The successful contractor will be expected to show flexibility, excellence in tenant support / liaison and work in partnership with the Contract Administrator / Building Surveyor to meet and exceed tenant expectation and levels of satisfaction.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 30 Jan 2020 | Award (award) | · | 6938b2b1-b2de-456c-8a70-744eed15c251-340462 |
more from Bolsover District Council
- Health and Safety Training - AWARD · 5 Dec 2025
- Tthe provision of a Property Security Contract - AWARD · 15 Oct 2025
- Positive Input Ventilation System - AWARD · 15 Oct 2025
- Flat Roofing Repairs and Replacement - AWARD · 6 Aug 2025
- Play Area Development - Bourne Place Play Area, Denby - AWARD · 4 Aug 2025
- Provision of Architects for RIBA Stages 0-3 for a New Build Community Centre and RICS Quantity Surveyors · £30,000 · 24 Jul 2025
- Playing Pitch Strategy and Assessment · 18 Jul 2025
- Go! Active Pool Plant Servicing - AWARD · 18 Jun 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Aseptic Suite & Dispensary Works - Architect & Principal Designer (Stage 0-3) · The Christie NHS Foundation Trust · £43,951
- Middlewich Police Station Refurbishment - CPA/SPU/2849P · Police & Crime Commissioner for Cheshire/Cheshire Constabulary · £72,545
- Bathroom refurb works · UNIVERSITY OF THE WEST OF ENGLAND · £20,979
- Ward 10 Refurbishment - Architect & Principal Designer · The Christie NHS Foundation Trust · £56,400
- PS-26-95 - Refurbishment of the Galleon Leisure Centre · East Ayrshire Council · £399,805
- Refurbishment and Improvements works at Adams Building · Nottingham College
- Refurbishment Works to Candlewick, Forncett Road, Tharston, NR15 2YB (Lot 2) · PROGRESS HOUSING GROUP LIMITED · £586,000
- Co-op Academy Medlock - Toilet Refurbishment · The Co-operative Academy of Manchester · £1
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.