Provision of Support on Internal Hazards Safety Assessment of the AP1000 GDA Issues

DEPARTMENT FOR WORK AND PENSIONS Published 18 Nov 2016 Contracts Finder

key details

Value£138,250
Statuscomplete
Category (CPV) 73000000
Deadline23 Aug 2015
Contract start24 Aug 2015
Contract end29 Jul 2016
SME suitableYes
OCIDocds-b5fd17-d0ede5ca-adc8-11e6-9901-0019b9f3037b

Award

SupplierValueDateStatus
GRS £138,250 29 Jul 2015 active

description

BACKGROUND TO THE PROJECT

1)Westinghouse Electric Company is the Requesting Party (RP) for the AP1000 Generic Design Assessment (GDA). During Step 4 of the GDA programme for the AP1000 reactor, ONR completed a significant amount of work in its assessment of this design.
2)ONR concluded that it was largely satisfied with the design and safety cases presented by the RP for the AP1000, although some issues remained and required further work. The additional work required to complete GDA was captured in the 51 GDA Issues reported at the end of Step 4 in 2011. Of these, six were Internal Hazards Issues and are summarised as:
GI‐AP1000‐IH‐01 GDA Issue, Revision 0 - Internal Fire Safety Case Substantiation;
GI‐AP1000‐IH‐02 GDA Issue, Revision 0 - Internal Flooding Safety Case;
GI‐AP1000‐IH‐03 GDA Issue, Revision 0 - Pressure Part Failure;
GI‐AP1000‐IH‐04 GDA Issue, Revision 0 - Internal Explosion Safety Case Substantiation;
GI‐AP1000‐IH‐05 GDA Issue, Revision 0 - Internal Missile Safety Case; and
GI‐AP1000‐IH‐06 GDA Issue, Revision 0 - Substantiation and Analysis of the Consequences of Dropped Loads and Impact from Lifting Equipment Included Within the AP1000 Design.
3)These GDA Issues should not be interpreted as a negative regulatory view of the AP1000 reactor design. Rather, they should be seen as evidence of the operation of an independent and robust regulatory process and a demonstration of ONR’s mission to provide efficient and effective regulation of the nuclear industry, holding it to account on behalf of the public.
4)The GDA Issues close‐out stage will be an in‐depth ONR assessment of the additional design and safety or security case evidence submitted in response to the GDA Issues. Scope and timescales for this stage will depend on the programmes identified in the resolution plans provided by the RP. The RP will have to submit evidence in accordance with the resolution plans and ensure that claims and arguments associated with the internal hazards issues are underpinned by robust evidence. The final submissions will update the:
Generic PCSR;
GDA Design Reference.
5)ONR anticipate initiating engagement with the TSC at an early stage, with technical support being provided once submissions from the RP become available.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
24 Sept 2015 Award (award) · ocds-b5fd17-d0ede5ca-adc8-11e6-9901-0019b9f3037b-75189-onr-265

more from DEPARTMENT FOR WORK AND PENSIONS

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.