gvtcx

A435 Cycleway Section 2.1 & Wellington Road

Gloucestershire County Council Published 6 Jun 2024 Contracts Finder

key details

Value£3,750,000
Statusactive
Category (CPV) 45000000
Deadline16 Jul 2024
Contract start9 Sept 2024
Contract end15 Aug 2025
Procedureopen
SME suitableYes
OCIDocds-b5fd17-cf25bf59-efee-49ea-b141-4f947c0ad888

description

This advert is intended to notify potential suppliers of the tender for the A435 Cycleway Section 2.1 & Wellington Road scheme.

The A435 Cycleway Section 2.1 works are located between the GWSR Bridge and Bishop's Cleeve roundabout, with the Wellington Road works located between Wellington Road and Central Cross Drive.

The works are located at two distinct sites. The first site, A435 Cycleway Section 2.1, is located north of the GWSR Bridge (approx. post code GL50 4SH) to Bishops Cleeve Roundabout (approx. post code GL52 8SF), and the second site, Wellington Road, located from Wellington Road Junction (approx. post code GL52 2AH) to Central Cross Drive junction (approx. post code GL52 2AH). This scheme is part of a wider strategic scheme to boost active travel provision within the county, through the creation of the Gloucestershire Cycle Spine. The overall scheme will implement a continuous cycleway for cyclists of all ages and abilities between the main hubs of Bishops Cleeve, Cheltenham, Gloucester, Haresfield and Stroud. In addition, this scheme will also install a section of sheet piling along the A435, which shall improve embankment stability and reduce continuous carriageway cracking.

The client is looking for a Principal Contractor to deliver the construction phase of this scheme.

Summary of Construction Phase key deliverables are as follows:

Provide suitable Traffic Management during the construction works.

Pedestrian access to residents always during the construction works.

Utility diversion works (arranged by GCC for PC to liaise/accommodate).

New drainage works and tie-in to existing.

A mixture of Highway, segregated footway / cycleway track and new shared use path construction.

Junction and carriageway realignments.

New traffic signals facilities across the route.

Streetlighting column installation and relocation.

Sheet piling installation along the A435 for 160m.

A summary of the outline programme is shown below:

Tender return: 16th July 2024

Award: Friday 9th August 2024

Anticipated Works Start Date: 9th September 2024

Completion: 15th August 2025

Overall Duration: 39 weeks

Indicative Value: £3.75m (£4.5m including VAT)

The proposed procurement route will be a single stage (Open Procedure) using the NEC4 ECC form of Contract, Option A Priced Contract with Activity Schedule.

Full details will be available in the tender pack om Procontract.

https://procontract.due-north.com/Advert?advertId=f2a5e8b6-9d0c-ef11-812b-005056b64545&p=696a9836-1895-e511-8105-000c29c9ba21

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
6 Jun 2024 Tender (tender) · 099f9586-9ee2-4218-b7bd-8271caa1a2a8-757270
2 Jul 2024 Tender (tender) · 99d5b304-dd83-4000-bd77-0fa9e39afe4e-763490

more from Gloucestershire County Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.