Redruth Revival Feasibility Study
key details
| Value | £24,708 |
|---|---|
| Status | complete |
| Category (CPV) | 79314000 +1 more |
| Region | South West |
| Deadline | 1 Jan 2019 |
| Contract start | 3 Jun 2019 |
| Contract end | 31 Dec 2019 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-cb5f149f-0c31-46ff-8de5-2857ea4001b7 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| pdp Green Consulting Ltd | £24,709 | 6 Feb 2019 | active |
description
We wish to commission a Feasibility Study which will examine a number of aspects of the site and consider some possible design options to inform the next stage of project development. We seek proposals from a team to undertake this work. The project is at the beginning of the RIBA Stages of Work at present.
We suggest that as a minimum the Study should examine:
Building structures - to establish the soundness of the roofs, walls and floors and the presence of any subsidence (recent or historic)
Services - to clarify what we know about the main utilities and services, including the condition and routes of drainage systems, some of which may be very old
Design and development constraints - listed building status, planning context, conservation and historic environment issues, freehold and leasehold legal documentation, party wall issues
Measured survey - perhaps not of all internal structures, but at least an external measured survey and floor levels.
Following the completion of these initial studies which we expect to take perhaps two or three months from appointment, we also want the successful team to create some design options and approximate costings which could then inform the next stage of project development and fund-raising. These should include the building currently in separate ownership which sits between and over parts of our freehold site.
We expect that the outputs of the project will be a series of technical reports covering the surveys and reviews listed above together with a number of approximately costed design options that we can use in order to undertake the next stage of our scheme which will involve further fundraising and the procurement of a design team to take the project up to full planning permission.
We hope that the Feasibility Study will be part-funded by the Architectural Heritage Fund and so bidders should familiarise themselves with the requirements set out in the AHF's Guidance Notes and Report Template for the Project Viability Grant scheme. One funding source for future stages of the project may be the Heritage Lottery's Heritage Enterprise programme.
In tandem with this technical and design work, Redruth Revival will continue to work with a range of partners, stakeholders and users in Redruth to inform and develop the next stage of our business planning process. This will include financial modelling for the revenue operations of a completed scheme and an assessment of the potential impacts (financial, environmental, social) of the project over the longer term. We would want the successful team to play a role in this consultation process, for example by means of presentations of design options to stakeholders, and this should be allowed for in your budget.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 22 Mar 2019 | Award (award) | · | 1ef2b4fb-4892-4c1e-95d5-75bb92b5e0c8-277954 |
more from Redruth Revival
- Redruth Buttermarket - Tender Award for PM & QS · £84,000 · 15 Oct 2021
- Tender for Development Appraisal Consultant · £8,000 · 14 Oct 2021
- Tender for Business Plan Consultant · £8,000 · 14 Oct 2021
- Tender for an Activity Plan Consultant · £8,000 · 14 Oct 2021
- Redruth Buttermarket - Tender for Architect-led Design Team · £200,000 · 13 Aug 2020
- Redruth Buttermarket - Tender for Project Manager & Quantity Surveyor · £75,000 · 9 Jun 2020
- Redruth Revival Feasibility Study · £25,000 · 11 Jan 2019
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Leeds Station Onward Travel feasibility Study - proposed approach to commissioning and appointment of consultants · Leeds City Council
- CASTLE Phase 2 Feasibility Study and Support · TEES VALLEY COMBINED AUTHORITY · £210,000
- Heat From Mines, Detailed Desktop Studies in the West of England · West of England Combined Authority · £100,000
- GR/Capability & Ambition Fund 2: Frome Valley Greenway Feasibility Study · Bristol City Council · £34,927
- Mortuary Feasibility Study on Behalf of the Coroners' Service · HAMPSHIRE COUNTY COUNCIL · £86,982
- Feasibility Study Connected Automated Transport · Tees Valley Combined Authority · £56,500
- CA15265 - NPTC - Skills for Floating Offshore Wind Feasibility Study (FLOW) · NPTC Group of Colleges
- MMDC-PROC-0014 - Middlesbrough Marks & Spencer Feasibility Study · Tees Valley Combined Authority · £50,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.