GB-Lowestoft: Cycle Bridge Design Project *Duplicated*
key details
| Value | £100,000 |
|---|---|
| Status | active |
| Category (CPV) | 71242000 +1 more |
| Region | East of England |
| Deadline | 10 Jun 2018 |
| Contract start | 1 Jul 2018 |
| Contract end | 21 Dec 2018 |
| Procedure | open |
| SME suitable | No |
| OCID | ocds-b5fd17-142c3ffa-d0d3-417d-bbcd-157f4d354601 |
description
A design in principle was completed by Sustrans in a previous Feasibility Report completed by them in April 2017. A preferred option was identified in that Feasibility Report which would enable crossing of all abilities on bicycles, pedestrians and pushchairs, to the east of the existing Network Rail footbridge. The design now requires further work and completion to enable Waveney District Council to become Planning Ready.As part of the vision in the Area Action Plan (AAP) it is highlighted that the need to reduce the impact of car travel through improved or new connections for walking and cycling provision. The existing footbridge at Constable Close is only a footbridge and is not Equalities Act compliant and unusable for prams, pushchairs or cyclists of all abilities. A new cycle & pedestrian footbridge across the railway would allow the cycle infrastructure to avoid the current pinch points and accident black spots on the A12 to the east and the A146 to the west, these are both shared crossings.
The main purpose of the bridge is to replace the already existing footbridge over the Lowestoft-Norwich and Lowestoft-Ipswich railway line with an accessible for all crossing.
Also there is the possibility of an extension to this bridge identified in the AAP to enable cyclists to cross over Lake Lothing. This is not a guarantee to happen but the design must enable the extension at a later date if required.
Additional information: Please use access code 526UVY6A22 to access the tenderbox.
documents
- https://www.contractsfinder.service.gov.uk/Notice/06eddbc9-ea55-4697-91c5-e958b88b06d4 , tenderNotice
- https://www.delta-esourcing.com/delta/respondToList.html?noticeId=319895638 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 17 May 2018 | Tender (tender) | · | 06eddbc9-ea55-4697-91c5-e958b88b06d4-216900 |
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- GB-Newcastle upon Tyne: Cost Manager and Contract Administrator · Northumbria University · £49,426
- Cost Estimating Framework · National Highways Limited · £12,000,000
- Construction Professional Services Delivery-Cost Management-Contract Award-Reserve Contractor · Home Office
- Construction Professional Services Delivery-Cost Management-Contract Award-Main Contractor · Home Office · £600,000
- Construction Professional Services Delivery-Multi Disciplinary Team-Awarded Contract-Reserve · Home Office
- Construction Professional Services Delivery-Multi Disciplinary Team-Awarded Contract-Main Contractor · Home Office · £57,000,000
- Cost Estimating Framework - Task Order - CEF04 Package 3 - Cumming Group FY 26/27 · National Highways Limited · £200,000
- Multi-Storey Car Park Review · Suffolk Coastal District Council and Waveney District Council · £61,400
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.