gvtcx

RA355744 - Firewater Pump Replacement

LondonEnergy Ltd Published 19 Jan 2026 Contracts Finder

key details

Statusactive
Category (CPV) 45000000
Deadline26 Jan 2026
Contract start20 Apr 2026
Contract end30 Nov 2026
Procedureopen
SME suitableYes
OCIDocds-b5fd17-13e2c69b-79eb-424f-969d-ead6305248bb

description

Please note that this advert is for pre-tender market engagement only. Tender is scheduled to be Published via the Delta eSourcing Platform on the 26th of January 2026.

Please email Lewis.atkinson@londonenergyltd.com to declare interest and to be included in the tender invite when it is published.

A breif description of Scope below. Please find full spec attached.

Within the EcoPark, there is a firewater ring main system consisting of:

1)2 x Firewater Pumps
2)1 x Sprinkler Header with level control (float switch start)
3)1 x Fire Water Ring Main (with pressure-controlled start capability)
4)40 x Isolation Valves
5)18 x Fire Hose Points
6)18 x Fire Hose Connections
7)20 x Fire Hydrants
8)1 x Crossover Pipeline (for pressure compensation - to be decommissioned and replaced with the jockey pump)

The Eco Park Firewater Pump Project aims to install two new diesel firewater pumps and integrate them with the London Energy DCS system. This will enhance the control, monitoring, and visibility of the fire protection system compared to the currently installed setup. Additionally, a new jockey pump will replace the existing crossover system to maintain pressure in the Firewater Ring Main.

In addition to the installation of two new firewater pumps and a jockey pump, this project requires enhanced visual, audible, and control capabilities. All components and alarms must be integrated with the SCADA system, ensuring seamless monitoring and control

  • B)Project Scope
  1. Replace the existing firewater pumps with two new diesel driven firewater pumps. Disconnection of the existing cables from the current firewater pumps and re-termination into the new firewater pump panel. Extending the existing cables via a JB or cable joint. Installation of any additional cables (to be specified and installed by the contractor).
  1. Select, procure and install a new jockey pump to maintain Ring Main pressure. Installation of any additional cables (power and control) for the jockey pump.
  1. Upgrade repeater panels to communicate all alarms and faults to the SCADA system.
4)Implement DCS-based control and monitoring of the firewater pumps and jockey pump through SCADA.
5)All technical documentation and drawings are to be provided to LEL by the selected contractor for upload to the London Energy SharePoint, by LEL.

?

  • C)Control Specifications

This section outlines the existing control and installation configurations, as well as the required upgrades.

Existing Control and DCS Specifications (Electrical):

  • Auto Start: Currently initiated via the "Firewater Pump Test Panel" located on the turbine mezzanine level and from the Sprinkler Header Level Switch.
  • Manual Start: Operated through local control panels at each pump and at various push buttons throughout site. Manual stop is only available via the engine choke on the diesel engine.
Indications Available:
oPump running
oBattery circuit healthy
oBattery charger healthy
oPump on demand
oFail to start
oLow oil pressure
oHigh water temperature
oLamp test
oAlarm acknowledgement

All above indications are repeated on remote repeater panels located in the Turbine Hall (East end).

Audio and visual alarms: Present on both local and remote panels.
No current control or status indication is available in the CCR via SCADA.

Fault Indication and Alarms (Current Local Control Panel):

oHigh water temperature
oLow oil pressure
oBattery charger failure
oBattery circuit failure
oFail to start
oPump on demand
oAlarm acknowledgment
oRepeater panels provide remote visual and audible alarms.
oThe local test panel enables auto start/stop of firewater pumps
oNo current DCS connectivity or SCADA monitoring of pump operation

Fault Indication and Alarms (New Local Control Panel to be installed):

The new firewater pump control panel (provided by SPP Pumps) will use a volt-free contact for a common fault alarm. Individual alarm indications will be shown locally via the HMI. Features include an integrated PCB board with volt-free contacts and designated inputs, dual 10A battery chargers and 12V DC batteries for ignition coil and motor starter.

Alarm and Status Indications:

oNot in Auto Mode
oPump Running
oPump on Demand (via Float, Pressure or Manual Start request)
oFailed to Start
oMains Supply Failure
oHigh Water Temperature
oLow Oil Pressure
oLow Engine Cooling Water Flow
oLow Fuel Level
oLow Engine Temperature
  • D)New Control Specifications

This section outlines the specifications for the new firewater pump control system to be installed by the selected contractor, including all hardwired electrical requirements, the selected contractor is expected to incorporate the existing manual and automatic start functions.

New Control System Specifications:

  1. Auto/Remote Start

Auto or remote start will be initiated from the Firewater Pump Test Panel. Interconnections required to enable this function are shown in the associated project drawings.

oAll interconnection work will be carried out by the selected contractor.
2.Manual Start

Manual start shall be initiated locally via push buttons installed on the new control panel at each firewater pump. These panels include an integrated HMI display.

  1. Local Indication and Fault Display

The new control system shall provide local indication of the following conditions via LEDs installed on the new repeater panels.

oPump Running
oHigh Water Temperature
oLow Engine Temperature
oLow Cooling Water Flow
oRemote Start Active
4.Repeater Panel Signal Integration

Pre-existing repeater panel cables will be reused. These will be terminated in the new repeater panels, which will display:

oPump Running
oFault Alarm
oNot in Auto Mode
oPump on Demand
oMains Failure
oFailed to Start

Interconnection between the new firewater pump control panel and repeater panels will be made using an IP67-rated polycarbonate junction box, installed locally at the new firewater pump.

  • oAll terminations will be completed by the selected contractor.
  1. Repeater Panel Construction

Repeater panels will be built on-site by a LEL-specified technician.

oAll components must comply with the appropriate SIL (Safety Integrity Level) as defined by selected contractor.
6.SWA Cable - Mezzanine Floor

A single 3-core cable, conforming to LPC Technical Bulletins 210 and 236 (TB210 and TB236), shall be routed between the junction box and the relay/start push-button station on the Mezzanine Floor for each firewater pump shall be installed by the contractor.

  1. SWA Cable - Firewater Pump Control Panel

A single 19-core SWA cable conforming to LPC Technical Bulletins 210 and 236 (TB210 and TB236), shall be routed between the junction box and the control panel on each firewater pump.

  1. Sirens

Existing orange mineral-insulated cables for the sirens on Panel 1 and Panel 2 must be reinstalled on top of the new control panels.

  1. A LPCB flow meter is to be provided and installed in accordance with LPC rules (technical bulletins) incorporating BSEN12845, with an integral "self-test" return loop for both pumps.

Existing Repeater Panel - Indications and Installation (Turbine Hall):

Current repeater panels provide the following indications:

1.High Water Temperature
2.Low Oil Pressure
3.Battery Charger Failure
4.Battery Circuit Failure
5.Fail to Start
6.Pump on Demand
7.Alarm Acknowledgement
8.Visual and audio alarms for remote fault indication
9.Local Test Panel for auto start/stop control

No DCS or SCADA connectivity for pump status or alarms

New Repeater Panel - Indications and Installation (Turbine Hall):

1.Common Fault Alarm - Visual and audible indication
2.Not in Auto Mode
3.Failed to Start
4.Pump on Demand
5.Pump Running
6.Mains Failure

Full DCS/SCADA Integration - All alarms and remote start/stop functions to be extended to SCADA, existing cabling will be reused for connectivity between new firewater pump control panels and repeater panels, Sirens to be reinstalled on top of new control panels

  • E)Jockey Pump Specifications

This section outlines the installation requirements for the jockey pump, including electrical, control, and mechanical specifications

1.Decommissioning:
oTwo "Dust Extraction Pump Discharge" pumps are to be disconnected, removed, and associated cables made safe.
2.Installation:
oA Jockey Pump will be installed in place of the "TY192 Dust Extraction Pump Discharge" pump.
oJockey pump to replace cross over pipeline for pressure compensation. Installation to be carried out by the selected contractor.
3.Electrical Supply:
oA new 415V 3-phase supply is required.
oOne of:
?4-core Conforming to LPC Technical Bulletins 210 and 236 (TB210 and TB236), , or
?3-core with bare copper earth, Conforming to LPC Technical Bulletins 210 and 236 (TB210 and TB236),

from an appropriate designated distribution board. Location to be determined by contractor.

  • oA lockable isolator must be installed near the jockey pump on a suitable stand. The appropriate loading and size of the jockey pump motor to be designed, selected, procured, installed and commissioned by the contractor.
4.Pump Specification:
oThe motor nameplate details must be provided to the E&I technician.
oFinal pump sizing is to be determined by the selected contractor.
5.Starter Panel:
oMust be redesigned to include:
?Control voltage protection and Primary voltage protection (a number of appropriately rated fuses for the control voltage and a suitable sized MCCB with thermal or CT overload).
?Motor protection.
oDesign and component selection to be carried out by the LEL E&I technician in collaboration with the contractor.
oDesign documentation and SIL certification to be provided.
6.Test Fire Pump Panel:
oTo be modified by the contractor to incorporate jockey pump activation based on header low pressure.
oJockey pump to have its own pressure switch independent of the Test Fire Pump Panel, which will need to include a cable from the Jockey Pump Starter Panel to the position of the new Pressure Switch to be selected, designed and installed by the contractor.
7.Pump initiation board:
oA pump initiation board is to supply in accordance with BS EN 12845. Pump initiation boards are designed to allow the initial setting and testing of sprinkler system pump initiation pressure switches in compliance with BS EN 12845. Each main pump has two pressure switches and jockey pumps have a single switch. The pressure switches can be isolated so that its function and cut-in pressure can be verified during system servicing. The special arrangement of ball and check valves means that even if all switches are isolated, a drop in system pressure will still initiate pump operation. As an additional safety measure, lockable ball valves are used to reduce the risk of them being accidentally closed.
8.Integration:
oThe jockey pump must be fully integrated into the DCS system by the selected contractor.
oSignals required from the jockey pump to DCS include "Tripped" signal in line with other alarm terminology.
  • F)DCS and SCADA Integration

DCS and SCADA Specifications

The selected contractor is responsible for designing and implementing integration of the fire pump system with the DCS/SCADA system.

1.All alarms (visual and audible) must be replicated in the SCADA interface.
2.Fire pump status (running, faults, etc.) must be visible in the CCR SCADA graphic interface, which is to be developed by valmet.
3.Remote start/stop and fault status for:
Jockey pump and Fire pumps must be available on SCADA (No requirement for a remote "Start/Stop" signal from DCS for the jockey pumps).
4.All SIL-rated instruments must be specified and documented by the contractor.
5.Fire pump header pressure is to be displayed in SCADA, integrated via the graphic interface.
6.All communication cabling must be specified by the contractor.
7.Any I/O racks required must be specified and integrated by the contractor .
8.PLC panels and I/O racking:
Specified and installed by the contractor.
All terminations to be completed by the contractor.
9.PLC Logic and Design:
Must be reviewed and approved prior to commissioning
Two new 12-core cables conforming to LPC Technical Bulletins 210 and 236 (TB210 and TB236), are to be routed via existing cable tray from Alarm Panels 1 and 2 to the "Central Gauge Board De-Min Control Panel" in the Turbine Hall.
10.Existing spare DCS Valmet I/O slot 8,16 Digital Input Card:
Wire numbers 720017 to 720032,are to be utilised for SCADA connections.
  • G)Contractor Responsibilities - Electrical
  • 1.Decommissioning Work

To be performed by the selected contractor:

Verifying circuits are de-energised ("prove dead")
Removal of redundant cabling from existing firewater pumps and panels
Removal of obsolete or unsuitable cable trays, containment systems, and ancillary fixings as required
  1. Installation and Terminations

The selected contractor will be responsible for the installation and termination of cabling and equipment, including:

Installation of new repeater panels as per specifications
Installation of junction boxes at the firewater pump locations to accommodate signal interconnections
Installation of cable tray systems near firewater pump sets for proper containment and support of cables
oAll tray work to be galvanised and painted with galvanised spray at cut ends and properly earth bonded.
oMetal Cable Ties to be applied in all instances
Termination of cables between:
oNew repeater panels
oBattery panels
oNew junction boxes
All local control panel terminations
Installation of cable between the jockey pump and the new junction boxes at the fire pumps to accommodate a "Tripped" signal back to the DCS.
End-to-end testing of all new and existing circuits and cables to ensure compliance and functionality.
Earthing Design to be submitted as part of the tender submission.

Cable Containment:

This section outlines the cable containment requirements for the project.

1.For the two cables running from the alarm panels in the Turbine Hall to the junction boxes at the fire pumps, the selected contractor is to:
oCalculate the appropriate cable tray sizing.
oAssess and communicate any requirement for scaffolding for installation.
2.For the 240V supply cables from the designated Power Distribution Boards to each fire pump:
oThe cable trays must be installed suspended due to the inaccessibility and hazards associated with the existing ducting (e.g. lifting metal covers and accumulated sediment).
oAll installation work to be carried out by the selected contractor.
3.For the cables between the junction boxes and the relay/start push-button stations on the Mezzanine Floor:
oSuspended cable trays are also required and must be calculated and installed by the contractor.
4.Additional ancillary tray work must be measured and installed for:
oOther control and power cables (e.g., 35mm² tri-rated cables) routed between the control panel frames and fire pumps.
oThis work is to be carried out by the selected contractor(s).

Diesel Day Fuel Tank Control

This section specifies the fuel tank overfill protection system for the diesel day tanks.

1.To prevent overfilling, the system shall include:
oA High-High Level Float Switch installed on the existing new tank, and
oA Solenoid Isolation Valve on the gravity-fed fuel inlet lines.
2.The control philosophy follows a fail-safe design:
oUpon detection of a high-high fuel level, the float switch signals the solenoid valve to close, preventing overflow.
oOnce the fuel level drops to a predefined safe level, the float resets, re-energising the solenoid valve to reopen, resuming normal operation allowing the operations to manually fill the Day Tanks.
3.This automatic level regulation:
oPrevents spillage,
oEnsures environmental compliance,
oAligns with critical fuel system safety standards.
4.The high-high level condition shall be annunciated on the control panel.
oAdditional cables and electrically controlled equipment (solenoids and valves) shall be selected and precured by the contractor.
oIntegration into DCS to be completed by valmet.

Battery Control Panels

This section outlines requirements for the Battery Control Panels associated with each fire pump.

1.Two Battery Isolation Control Panels are to be mounted to the frames of the fire pump control panels. Additionally, two junction boxes are to be mounted on each fire pump control panel.
2.From each battery pack, two 35mm² tri-rated cables are to be routed:
oTo the battery isolation panels,
oThen to the fire pump terminals for solenoids (for "Auto" and "Manual" start functions),
oIncluding earth connections.
3.Two new 240V supplies cables are to be installed:
oFrom the designated power distribution boards to each fire pump control panel.
4.One cable is to be routed:
oBetween the junction boxes and the battery isolation panels on each fire pump.
  • H)Contractor Responsibilities - Mechanical
  1. Decommissioning Work

To be performed by the selected contractor:

Verifying stored energy for any pipework removal has been completed by LEL
Removal of redundant pipework and fittings from existing firewater pumps & making good
Removal of existing pumps and diesel drivers and any ancillary fittings as required
  1. Installations

The selected contractor will be responsible for the installation of the following equipment, including:

Installation of two new pumps: : SPP TD15A Horizontal Split Case Pump coupled with Matched Diesel Engines and Combined Diesel Tanks.
Installation of one new Jockey pump and Electric Motor: Discharge Jockey Pump pressure to maintain fire ring main at max 7 bar. Suction pressure will be Plant Auxiliary Cooling Water Pump Suction pressure. Pipework Tie-In's will be site run to existing Firewater Pump suction and discharge pipework local to the pump.
Installation of new jockey pump valves (Zurich will come in to check required valve spec):
ox1 Inlet valve
ox1 Outlet valve
ox1 Drain valve
ox1 Vent valve
ox1 NRV
Existing isolation valves to be used for original fire pump sets.

Timeline for Installations, commissioning and handover (including drawings and training) to be completed by selected contractor.

Firewater Pumps:

This section outlines the mechanical required works for the firewater pumps.

5.Diesel - Supply, isolation standard (Additional valves required), protection, control and instrumentation. Use SPP W00-003E installation specification.
oUse SPP W00-003E installation specification.
6.Engine Exhaust - Contractor to determine whether existing exhaust system is suitable for SPP Diesel Engine specification.
7.Suction/Discharge Pipework - Field run into existing firewater pump pipework and compliant with [ASME B31.3.]. ASTM A106/B Sch 40 with fittings and Flanges compliant with existing pipework.
8.Pipe fittings and supports - Compliant with BS EN 12845
9.Painting - Any new pipework to be prepared with x2coats of primer and x2coats of red gloss.
10.Civils and structural - Contractor to determine new footprints, ensuring compatibility of existing plinths for gross weights, to accommodate seating of new pumps.

Jockey Pumps:

This section outlines the mechanical required works for the jockey pumps

1.Suction/Discharge Pipework - Field run into existing jockey pump pipework and compliant with [ASME B31.3.]. ASTM A106/B Sch 40 with fittings and Flanges compliant with existing pipework.
2.Civils and structural - Contractor to determine new footprints, ensuring compatibility of existing plinths for gross weights, to accommodate seating of new pumps.
3.Pipe fittings and supports - Compliant with BS EN 12845
4.Painting - Any new pipework to be prepared with x2coats of primer and x2coats of red gloss
  • To access this competition: login to https://suppliers.multiquote.com and view the opportunity RA355744. Not registered on MultiQuote - visit https://suppliers.multiquote.com then register and quote RA355744 as the reason for registration. Any queries please contact MultiQuote on 0151 482 9230.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
19 Jan 2026 Tender (tender) · 1848d445-85b4-4a92-8cfc-e38f7a33c26c-879706

more from LondonEnergy Ltd

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.