Analysis to inform ORR's RIS3 Efficiency Review
key details
| Value | £340,000 |
|---|---|
| Status | complete |
| Category (CPV) | 72221000 |
| Deadline | 30 Oct 2023 |
| Contract start | 4 Dec 2023 |
| Contract end | 29 Apr 2024 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-c306dfa0-bafc-465f-aa05-9e463eba9cd2 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| CEPA LLP | £279,275 | 7 Dec 2023 | active |
description
Later in 2023, the government will publish its draft RIS. This includes the proposed requirements to be delivered by National Highways, and the financial resources to be provided by the Secretary of State (the SoFA). National Highways' Draft Strategic Business Plan (SBP) details its plans for delivering the requirements set out in the Draft RIS.
During the Efficiency Review, we undertake a detailed review of the Draft SBP to confirm that National Highways' plans will deliver the governments requirements (as set out in its Draft RIS) and do so in a way that represents an effective and efficient use of public money.
The Efficiency Review will consider whether National Highways' plans have been appropriately costed and will deliver the government's requirements in an efficient manner. However, our advice is not limited to cost, and efficiency. We will also evaluate the quality of National Highways' plans to ensure they provide a robust basis for delivery.
Furthermore, we advise government on the performance requirements and targets included in the RIS3 Performance Specification. It is our role to ensure that requirements and targets are sufficiently stretching, supported by appropriate plans and that the RIS package as a whole is challenging and deliverable with the funding available.
For context, the second Road Investment Strategy - containing the RIS2 Performance Specification - can also be found on the Department for Transport's website (Road Investment Strategy 2 (RIS2): 2020 to 2025 - GOV.UK (www.gov.uk))
This commission will inform ORR's advice in each of the areas set out above. To meet ORR's requirements, this commission has been subdivided into the following five lots:
Lot 1: Operations, maintenance, renewals and digital
Lot 2: Enhancements
Lot 3: Safety
Lot 4: Environment
Lot 5: Economic advice
Successful bidders will be responsible for scrutinising aspects of the Draft SBP and providing expert advice and analysis. For each lot, the final deliverable will be a report setting out the consultant's findings. ORR will draw on these reports when developing its advice to the Secretary of State. The advice itself, and the opinions it contains, remain the responsibility of ORR.
The ORR project team and consultancy teams will need to work in an integrated manner during the Efficiency Review. In some cases, the boundaries between various lots are overlapping. Therefore, consultants will also need to liaise with each other during the process.
Direct engagement with subject-matter experts within National Highways will be required. National Highways and ORR will facilitate interviews and workshops for this purpose. Meetings will typically be attended by both consultants and ORR. The ORR will submit requests for data and information to National Highways on the consultants' behalf via an agreed process for the Efficiency Review.
documents
- https://www.contractsfinder.service.gov.uk/Notice/58af78db-4bd3-4289-b495-1f5b4b9637aa , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/5c16f647-e871-4cb5-b323-6aa3420b1c17 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/65e96183-63e1-49d7-b434-68868d288ae7 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/6f9dfb84-0a5f-403c-a84e-eb875ccfcdda , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/7f57b5ab-2e1d-4d6c-83e6-9c3769703ae7 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/8f5394ee-1072-429b-ae43-476d57570389 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/aae78e3c-975d-4ef8-bc48-2ba7b63f8e31 , biddingDocuments
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 28 Sept 2023 | Tender (tender) | · | 58af78db-4bd3-4289-b495-1f5b4b9637aa-684140 |
| 14 Dec 2023 | Award (award) | · | b24874ca-4b9c-47e9-b2e8-2e0491388d78-705379 |
more from OFFICE OF RAIL AND ROAD
- Fare enforcement T&Cs focus groups and call for evidence follow-up interviews · £45,890 · 6 Mar 2025
- ORR Suite of Contracts · £27,650 · 6 Mar 2025
- Fare enforcement staff research · £87,825 · 6 Mar 2025
- Strategic Regulatory Advice · £35,000 · 6 Mar 2025
- Occupational Health & EAP · £26,979 · 6 Mar 2025
- Engineering Roles · £45,000 · 5 Mar 2025
- TDL Enhancements and Support · £146,250 · 23 Jan 2025
- Lenovo ThinkPad X13 Yoga Gen 4 x 15 · £20,264 · 16 Jan 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Criminal Justice Data Spine Delivery · Home Office · £2,500,000
- Asset Systems Review · THE GUINNESS PARTNERSHIP LIMITED · £60,000
- 260065 Strategic Consultancy Support · Queen's University Belfast · £448,500
- ITT - Archive Strategic Review (UID 267) · Historic England · £25,000
- TEN-2526-048 (PCR15) - Modern Agile, Product Led Delivery (MAPD) Pilot · National Employment Savings Trust (NEST) · £450,000
- Adults Services Improvement Programme · Bedford Borough Council · £5,357,000
- Travel to School Framework Call off · North Northamptonshire Council
- Rio Gap Analysis · Kent and Medway Mental Health NHS Trust · £19,620
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.