NEA - EcoSF3 - Lot 4 - Hebden Bridge Flood Alleviation Scheme Modelling
key details
| Value | £79,820 |
|---|---|
| Status | complete |
| Category (CPV) | 79930000 |
| Region | Yorkshire and the Humber |
| Deadline | 27 Dec 2022 |
| Contract start | 30 Jun 2023 |
| Contract end | 9 Apr 2024 |
| Procedure | selective |
| SME suitable | No |
| OCID | ocds-b5fd17-bbefca52-17bc-4853-aaf7-d814837dd51d |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| AECOM Ltd | £79,820 | 28 Dec 2022 | active |
description
The Environment Agency (the client) is progressing a flood alleviation scheme in Hebden Bridge and have been investigating the removal of 5 barriers to fish passage (one on the River Calder, four on Hebden Water) either by fish pass, easement, weir removal, or partial weir removal. The removal of barriers to fish passage will provide mitigation measures or environmental enhancements as part of the flood alleviation scheme.
The Environment Agency have outline designs for modifications to each of the weirs and are now looking to progress the detailed design of Mayroyd Weir (River Calder) only. This is to inform a Listed Building Consent application for modification of this weir and the Water Environment (WFD) Regulations compliance assessment. The Listed Building Consent application will inform a planning permission application submission for the wider scheme and therefore needs to be prioritised. Outputs for the Listed Buildings Consent application are stated below in the Scope. Detailed design of the remaining weirs will be progressed at a later date once planning approval for the wider scheme has been granted.
The Hebden Bridge FAS is at risk of causing a deterioration in status or prevent the objectives of the Water Environment Regulations 2017 (formerly WFD) being met. Modification to Mayroyd Weir (in the form of partial removal and associated upstream benefits from reducing flow impoundment) is considered to be suitable mitigation to prevent the need for a Regulation 19 approval under the WER).
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 1 May 2024 | Award (award) | · | afacbadb-66b6-447a-884f-2f1dafcf16ab-746671 |
more from Environment Agency
- KSL NW MMF BARKING BARRIER · £102,301 · 29 Jul 2026
- Blaydon Quarry Landfill Gas Monitoring · £63,233 · 29 Jul 2026
- IMx - Phase 2 · £592,730 · 29 Jul 2026
- YNE AOMR Lot 1 Asset Recon Nunnington Channel Works · £76,486 · 29 Jul 2026
- KSL - Nav - East Farleigh Asset Refurbishment · £7,490,000 · 28 Jul 2026
- EAN - AOMR - East & National Eel Pass Programme · £4,791,694 · 28 Jul 2026
- NW - AOMR - Lot 2 25-27 GMMC MEICA D&B Package · £1,200,000 · 28 Jul 2026
- YOR - CDF - Tidal Ouse Left Bank Saltmarshe - SOC-OBC (ESE) · £64,282 · 28 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Accessibility and Inclusion Consultant for the New Wing at the National Gallery · National Gallery · £200,000
- Penrith PM Further Design AECOM · DEPARTMENT FOR ENVIRONMENT, FOOD AND RURAL AFFAIRS · £20,000
- Temporary Car Park at Weybridge · DEFRA · £19,827,232
- NBC PR33 Design Guardian · DEFRA · £1,500,000
- Lowestoft Windows replacement RIBA 5 to 7 · Defra · £72,659
- Halewick Lane Battery Energy Storage Site - Phase 3 · West Sussex County Council · £15,000,000
- Electrical Design of the Emergency Lighting System at the Barbican · The Mayor and Commonalty and Citizens of the City of London · £75,735
- NCP PR36 B445 Redesign Contract · DEFRA · £1,200,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.