Support and Maintenance for the Electricity Distribution Network Model
key details
| Value | £50,000 |
|---|---|
| Status | complete |
| Category (CPV) | 72220000 +1 more |
| Deadline | 7 Sept 2018 |
| Contract start | 28 Sept 2018 |
| Contract end | 31 Mar 2020 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-bb383262-af96-45f9-956d-daf629bdeb9e |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| TNEI Services Ltd. | £44,860 | 25 Sept 2018 | active |
description
BEIS wishes for the provision of ongoing maintenance and support for the DNM, the provision or proposal of ad-hoc model developments where available and to ensure changes to the model are properly tested and integrated, to ensure analysts can use the model effectively to meet policy needs.
The Electricity Distribution Network Model (DNM) consists of a Power Flow Model and an Investment Model to model electricity distribution network reinforcement costs associated with different peak demand profiles, driven by general electricity demand and different technology/intervention uptake on both the demand and supply sides.
The model is used alongside BEIS's other GB electricity market modelling capability to provide a complete picture of the future costs to the electricity system and is rooted in the work undertaken as part of the legacy Smart Grid Forum's Workstreams 3 and 7.
The support and maintenance BEIS wishes to commission must ensure BEIS analysts can use the model effectively by assisting them in setting up inputs, creating output templates and resolving technical issues with the working environment. The contractor will be responsible for dealing with issues that cannot be resolved by the in-house team, for providing training and for providing expert tailored support.
Further responsibilities of the contractor include the provision or proposal of ad-hoc model developments where possible as well as ensuring changes to the model are properly tested and integrated.
Additional information: How to Apply:
If you wish to take part in this procurement please see the attached Tender documents attached to this Notice and send your completed Proposal to Birgit Wosnitza and Nazish Choudery via email as stated below.
Any late submissions will not be considered. BEIS reserves the right to halt the procurement process and to not award a contract. BEIS will not be held liable for recovery of costs from unsuccessful bids if a contract is not awarded. All costs will be borne by the bidding organisations. If a contract is created it will be upon BEIS Short Form Terms and Conditions, which are available on Contracts Finder with this notice. Completed tender submission must be returned by email to Birgit.Wosnitza@beis.gov.uk and Nazish.Choudery@beis.gov.uk by 11am on 7th September 2018. After reviewing and evaluating the written proposals, BEIS may decide to hold bid clarification meetings with suppliers. If successful and upon contract signature, the supplier is expected to attend a kick-off meeting taking place on 28th September 2018 (or shortly thereafter). Project completion is required by 31st March 2020.
documents
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/927bde84-9752-423d-a8d2-8b23bd26726e , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/d2e81b28-7ee4-489f-bae7-7116feec18c4 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/f02ca1b2-6c7a-4e5f-b8c0-4ea50dcd804e , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/b9ad6ae2-37f5-4969-931a-e8ceae14027c , tenderNotice
- https://www.gov.uk/government/collections/quality-assurance-tools-and-guidance-in-decc , biddingDocuments
- https://www.gov.uk/government/publications/dynamic-dispatch-model-ddm , biddingDocuments
- https://www.ofgem.gov.uk/ofgem-publications/56824/ws3-ph2-report.pdf , biddingDocuments
- http://www.smarternetworks.org/project/nia_nget0154/documents , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 9 Nov 2018 | Award (award) | · | 4c0d073d-edb9-4ca6-bed1-facff62eadb8-251319 |
more from Business Energy and Industrial Strategy
- Delivery Partner 2 (DP2) - WH:SHF and WH:LG · 11 Sept 2025
- Heat Network Efficiency Scheme - HNES MAIN · £2,961,208 · 5 Nov 2024
- Re-procurement of Hydrogen Legal Advisors · 1 May 2024
- Technical Assistance Facility 2 - Pre-Tender Market Engagement · 14 Aug 2023
- APGB Reprocurement - Suppliers Event · 6 Jul 2023
- Medicines Manufacturing Skills and Training Consultation · 21 Apr 2023
- Sizewell C Legal Services Contract · £7,500,000 · 31 Mar 2023
- Local Authority 'Capability' and 'Capacity' Building Grant Funding Pilot Evaluation · 9 Feb 2023
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- SMCR Project - Innovation and Delivery Partner · FCA · £318,830
- Bus Franchise - Customer Workstream Service Design Implementation · West Yorkshire Combined Authority · £6,000,000,000
- Digital Contingent Labour Framework · THAMES WATER UTILITIES LIMITED · £0
- Hands on Technology SR2911423500 · H M REVENUE & CUSTOMS · £2,500,000
- Provision of Data, Solution and Technical Architecture Services · Office for National Statistics
- HMPO Cyber Security Services – Contract Modification (Additional Services) – Regulation 72(1)(b · Home Office
- Cloud Configuration Improvements · West Yorkshire Combined Authority · £85,000
- Senior Technical Architect · Cardiff and Vale University Health Board
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.