gvtcx

WP15 Final Highways Scope - Old Oak Common (S4) Station

Balfour Beatty VINCI Systra JV Published 21 Aug 2025 Contracts Finder

key details

Value£20,000,000
Statusactive
Category (CPV) 44212400 +1 more
RegionLondon
Deadline29 Aug 2025
Contract start16 Aug 2026
Contract end1 Dec 2028
SME suitableNo
OCIDocds-b5fd17-b9e74b50-fd16-4bb2-9e8b-7bc6a60c5dbb

description

WP15 Final highways scope

The OOC Lane realignment & Final highways scope package consists of:

Removal of all existing highway surfacing and street furniture (is there any to be retained / relocated or does it include disposal?)

Installation of any temporary critical highway furniture (e.g. Street Lighting, Barriers) required to carry out the works

Requirement to maintain a 2m wide footpath to be used by the public throughout the construction of the package, the subcontractor is to include the installation and maintenance of this public footpath, and relocation as required to suit the construction sequence.

The excavation of the existing highway down to final formation level, and any other necessary levels required to enable temporary works or sequencing

All temporary works required for the construction of the works, including any access requirements

Assessments to structures, utilities, properties, which may be affected by the works, as required to satisfy client, Contractor and/or 3rd parties requirements

Removal and disposal of all current utilities in the highway.

Installation of OOC Lane footpath retention structures

Installation of any other required Highway Civils

Installation of all highway and foul drainage

Installation of UKPN 132kV & 33kV duct routes, inclusive of any tunnel / subterranean system and the required temporary works

The removal of any installed temporary works and the construction of the highway

The installation of all highway furniture and its required infrastructure (traffic lights incl of ducting, islands, street lighting incl of ducting etc)

Removal of temporary works installed by others to facilitate utility connections at the north and south end of the

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
21 Aug 2025 Tender (tender) · 44b34daa-4df3-432a-8263-cf7c34fde72a-860311

more from Balfour Beatty VINCI Systra JV

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.