Navigation Waterways Benefits Assessment
key details
| Status | complete |
|---|---|
| Category (CPV) | 71311300 |
| Deadline | 6 Oct 2021 |
| Contract start | 10 Nov 2021 |
| Contract end | 31 Mar 2022 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-b48ecfa6-eb58-4f32-a545-e408c4760366 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Jeremy Benn Associates Ltd T/A JBA Consulting | £47,430 | 8 Nov 2021 | active |
description
This Section sets out the Authority's requirements:
Support the National Navigation Team in further developing the benefits assessment evidence to inform the strategic business case for the navigable inland waterways operated by the Environment Agency.
- A.Requirement
Support the National Navigation Team to prepare "whole" waterway assessments for a select set of benefits: (i) recreation, health and wellbeing; (ii) flood protection; (iii) water resources; (iv) sustainability (namely biodiversity and net zero carbon); and (v) local economic impacts.
The assessments for flood protection and water resources should apply the existing methodologies used by the Environment Agency. The approach to recreation, health and wellbeing shall develop the approach tested in a previous commission completed in 2021 for the EA. The approach to sustainability and local economic impact assessments will need to be developed.
The aim will be to provide an improved 'place-based' assessment accounting for the circumstances of the local population, including socio-economic profile and availability of green/blue space.
The selected waterways for a complete assessment are:
| - | Wye & Lugg |
| - | Lydney Harbour |
| - | Thames |
| - | Rye Harbour |
| - | Great Ouse |
| - | Nene |
The benefits assessment shall use the approach developed in the 2021 commission (attached).
The benefit assessment for sustainability and local economic impacts shall also be completed for:
| - | Stour |
| - | Medway, |
| - | Ancholme, |
| - | Welland and Glen |
| - | South Forty Foot Drain |
Deliverables: Present the results for each waterway requiring a complete assessment as a summary report and presentation. Present the results for the waterways requiring assessments for sustainability and local economic impacts as an addendum to the reports completed in 2021 for those waterways.
- B.Tasks
Please account for the following tasks:
- Project start-up meeting(s) and data and method share.
- Benefits assessment per waterway.
- Reporting.
- Resource estimate per waterway and per benefit category.
We will agree the format for reporting the assessment for each waterway as part of the project start-up template. We expect that this will include summary reports for each waterway, plus a set of guidance notes detailing the assessment method for each benefit type, the data sources and analytical steps.
The headline results, findings and recommendations for next steps shall be presented to EA teams.
Regular progress reporting meetings shall be included.
documents
- https://defra.bravosolution.co.uk , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/77483a25-15e8-4f21-8022-de7c94932229 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 14 Sept 2021 | Tender (tender) | · | 77483a25-15e8-4f21-8022-de7c94932229-468564 |
| 8 Nov 2021 | Award (award) | · | f046500f-946a-4022-96b1-c77ce4c2acbf-483486 |
more from Defra Network eTendering Portal
- Professional Services TPP Communication to Market · £1 · 19 Feb 2025
- Print and Postal Services TPP Comms to Market · £1 · 19 Feb 2025
- Communications and Marketing TTP Comms to Market · £1 · 19 Feb 2025
- Employee Benefits and Wellbeing TPP Comms to market · £1 · 19 Feb 2025
- APHA Courier International Specialist · 15 Jan 2025
- P-37177 Service Contract for DNA Analyser/KingFisher Ex robots/Thermal Cyclers · 7 Jan 2025
- Environmental Land Management Payment Rate Development and Verification · £1,200,000 · 12 Dec 2024
- Local Air Quality Management (LAQM) Support Contract · 4 Nov 2024
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Provision of Various Consultancy Services for the Energy Efficiency Retrofit Programme Wave 3 · Epping Forest District Council · £294,850
- Northumberland Line Business Realisation and Monitoring and Evaluation · Northumberland County Council
- Barrow Multi Modal Transport Study · Westmorland and Furness Council
- SW- DCIS- River Lemon, Copperhouse Gate and Portreath ECC PM - CCS LOT 1 · Environment Agency · £368,411
- Award of 181304 Community Hall Feasibility Study · Moray Council · £40,175
- Retrofit works consultancy · London Borough of Enfield · £70,200
- Mass Rapid Transit - Further Modelling · Milton Keynes Council · £120,000
- M49 Link Construction · South Gloucestershire Council · £100,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.