Build of the DCP ILW Extensions

Dounreay Site Restoration Limited Published 14 Oct 2018 Contracts Finder

key details

Statuscomplete
Category (CPV) 45000000
Deadline23 Mar 2018
Contract start9 Oct 2018
Contract end1 Sept 2021
Procedureselective
SME suitableNo
OCIDocds-b5fd17-2dfee9cb-40c6-460e-a39d-e5a9020c5cd2

Award

SupplierValueDateStatus
John Graham Construction Limited £22,500,000 8 Oct 2018 active

description

The scope of the works is for the construction of a new shielded Intermediate Level Waste (ILW) Drum Store Extension and an Unshielded Waste Store Extension for shielded waste containers to the existing Dounreay Cementation Plant (DCP) complex comprising of:

Procurement and construction of a large scale reinforced concrete store, construction of a fully clad portal framed 'lean to' structure with integral shield wall, substructure and external walls to provide the required radiological shielding;

Take on the role of Principal Contractor and establish a Delineated Site to control access and egress to the works and where all work activities are covered by the Contractor's safe systems of work;

Electrical and Mechanical installation works for the Stores and interfaces with the existing DCP Import Export Facility;

Procurement, manufacture and installation of shielded doors;

Procurement, manufacture, testing and installation of a lid lifting hoist;

Procurement, manufacture, testing and delivery of a modified 65 tonne bogie and rail system;

Provision of a control room that incorporates the electrical, control and instrument interfaces between the various systems in the new shielded ILW store extension;

Heating, Ventilation & Air Conditioning systems for the Stores;

Interactions with the Contractor appointed for the design, supply and installation of the facility cranes; and

Functional Testing (Setting to Work) of the new ILW store extensions, covering all plant & equipment including the compilation of all testing / commissioning procedures / instructons to the satisfaction / prior approval of the Employer's nominated representative. All testing carried out via a combination of Factory Acceptance Tests (FATs), Site Acceptance Tests (SATs) and Plant Walkdown Inspections (PWDS) as appropriate.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
16 Feb 2018 Tender (tender) · c2197b44-2549-433e-a79b-79e3ae05c623-199343
14 Oct 2018 Award (award) · 947a8b8f-5a6a-4392-b7d6-8889eb69d6b4-246178

more from Dounreay Site Restoration Limited

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.