Supply and Install of Uninterrupted Power Supply to BACS Control Panels
key details
| Value | £50,000 |
|---|---|
| Status | complete |
| Category (CPV) | 31154000 |
| Deadline | 9 Dec 2024 |
| Contract start | 8 Jan 2025 |
| Contract end | 31 Mar 2025 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-a759ce32-b4e1-4a9b-8350-84a9e4a4cabd |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Advanced Power Technology Ltd | £45,180 | 13 Jan 2025 | active |
description
The contract is for a single supplier to Supply and Install of Uninterrupted Power Supply to BACS Control Panels at The Pirbright Institute, Ash Road, Pirbright, Surrey, GU24 0NF.
See Appendix E - Contract Scope.
PROJECT SCOPE AND OBJECTIVES
The Brooksby Building at The Pirbright Institute (Pirbright) will be a high containment facility for work on high consequence pathogens such as foot-and-mouth diseases virus (FMDV) when fully operational in 2026.
As part of the post-construction 'Day 2' works there is a requirement to carry out additional works to the Building Automation and Control System (BACS) within the Brooksby Building to ensure it is fully aligned with the primary system used across the rest of the Pirbright site.
The following package of work has been funded:
- Installation of Uninterrupted Power Supply (UPS) to critical BACS Control Panels
Equipment - 1 x Large UPS Unit
Riello 30kVA Master MPS (6 Pulse Rectifier, 384VDC Battery, UPS to be fitted with a Multicom 384 comms card to be wired by Pirbright appointed contractor.
Equipment - 20 x Small UPS units
Sentinel Pro single phase on line 1kVA (0.8kW) 240v a.c.
Materials - As required
All required materials to be included: Cable, containment, Unistrut etc.
Installation Large UPS unit
Installation of 1 large UPS to 415v a.c. 3ph distribution board 50-DB-06-A-MECH rated at 100Amp complete with bypass switch fed from 50-SB-01-A at the main LV switch board on the AHU deck. This is inclusive of re-routing SWA and black plastic coated metallic flexible conduits. Install a Unistrut base to keep the UPS off the concrete with a clearance of 100mm.
Installation 20 Small UPS Units
Installation 20 Sentinel Pro UPS Units at locations indicated in drawings, external to control panels to give best possible ventilation. The "shelf" to be constructed of Unistrut and installed at a height to be serviceable and not to cause obstruction or in a position that may pose a concern to engineering team members.
Commissioning and testing All units
Test and commission all the above UPSs with installation to BS7671 electrical installation standard
Documentation ALL
Updated drawings showing site installation works Testing and commissioning results
To also be included in tender:
| • | Delivery of all materials to site |
| • | Production and issue of a programme of works |
| • | Provision of O&M Manual |
| • | Project management |
documents
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/15804b58-ce2d-45d7-99ed-7f751ccfb9a9 , submissionDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/28d9352e-b173-4df7-b0c2-52fd665a3680 , contractDraft
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/2b17d4e5-e0a3-4d6f-8a63-30b3058e470d , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/37efd506-db4d-4e47-8f15-d524eb1e0bb2 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/4860aa8d-d044-40e2-8462-a722d3be8334 , technicalSpecifications
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/544dc4a9-4bb8-4a56-837d-140cee4656db , evaluationCriteria
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/55832781-21d5-4775-b10e-0f19a9bdfc97 , technicalSpecifications
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/58e1ba52-32c7-4195-847f-f53e303bff34 , technicalSpecifications
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/7023b333-b1f4-4aa3-b2a3-864515613530 , submissionDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/709b6370-e603-47c9-9e6e-e4bc2e877c1f , submissionDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/7c1ea8b2-2f68-47ca-8fca-9f8ebb139d0e , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/af5c0bc1-3155-4b80-90ca-bb6c61699d71 , technicalSpecifications
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/dd0f2eac-f7e5-4fa0-8e10-60752422b19f , technicalSpecifications
- https://www.contractsfinder.service.gov.uk/Notice/df64cc01-8ea0-40ab-a03b-f6cb96558482 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
4 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 12 Nov 2024 | Tender (tender) | · | df64cc01-8ea0-40ab-a03b-f6cb96558482-797748 |
| 19 Nov 2024 | Tender amendment (tenderAmendment) | · | df64cc01-8ea0-40ab-a03b-f6cb96558482-803689 |
| 29 Nov 2024 | Tender amendment (tenderAmendment) | · | df64cc01-8ea0-40ab-a03b-f6cb96558482-806809 |
| 20 Feb 2025 | Award (award) | · | f1a15dc0-cc78-4b23-a5a7-337e96ae00de-818721 |
more from THE PIRBRIGHT INSTITUTE
- Provision of Occupational Health and Wellbeing services · £55,000 · 21 Jan 2025
- CHP LTHW Heat Recovery Principal Contractor · £315,000 · 2 Dec 2024
- Project Management re. Brooksby Building BACS additional works · £100,000 · 8 Nov 2024
- ISO 11 Incinerator Life Extension Project - WP10 Hydraulic System Replacement Project · £50,000 · 31 Oct 2024
- ISO 11 Incinerator Life Extension Project - CEMS · £130,000 · 14 Oct 2024
- ISO 11 Incinerator Life Extension Project - WP6 Diesel Tank Replacement · £30,000 · 24 Sept 2024
- ISO 11 Incinerator Life Extension Project - WP 5 Refractory Replacement · £450,000 · 9 Sept 2024
- Fire Alarm and Associated Systems Maintenance Contract · £40,000 · 10 Jun 2024
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Local and Network Cabinet UPS Provision (GCU) · Glasgow Caledonian University · £72,220
- Maintenance Contract for Starkstrom Theatre Pendants, IPS (Isolated Power Supply) and UPS (Uninterruptible Power Supply), TCP (Theatre Control Panels) and Operating Lights under HTM 06-01 PA23 for a hospital environment · NORTH CUMBRIA INTEGRATED CARE NHS FOUNDATION TRUST · £250,000
- UPS Battery Supply and Installation · University Of Edinburgh · £72,862
- Maintenance of UPS/IPS Power Supplies · Leeds Teaching Hospitals NHS Trust · £86,422
- Maintenance of UPS/IPS Trust wide · Leeds Teaching Hospitals NHS Trust · £124,039
- Uninterrupted Power Supply (UPS) unit support · Royal Papworth Hospital NHS Foundation Trust · £53,013
- Servicing and Replacement of Uninterruptible Power Supply (UPS) Equipment on the NRS Limited (Dounreay) Site · Nuclear Restoration Services Limited (Dounreay) · £490,000
- BE24202 - UPS Replacement System · UK SHARED BUSINESS SERVICES LIMITED · £11,913
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.