Provision of support to GDA for the UK HPR1000 on OPEX/OEF relating to design for decommissioning

Health & Safety Executive Published 24 May 2019 Contracts Finder
The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£110,209
Statuscomplete
Category (CPV) 73000000
Deadline9 Feb 2019
Contract start13 May 2019
Contract end29 Feb 2020
Procedureselective
SME suitableYes
OCIDocds-b5fd17-a4ba8e80-a8ce-4ec4-9f69-e3c7ba0f94e8

Award

SupplierValueDateStatus
Wood Plc £110,209 29 Mar 2019 active

description

ONR is seeking to engage one of the Technical Support Contractors (TSC) appointed on Lot 2 of its Technical Support Framework. The TSC is required to asked to undertake a review of the decommissioning of PWRs and other Nuclear Power Plants (NPPs), and the application of design for decommissioning, in order to identify good practices and OEF relevant to design for decommissioning of PWRs. The review should focus on collating and evaluating information on PWR designs with the greatest similarities to UK HPR1000. Review of OEF for plants other than NPPs should only be undertaken if considered relevant/potentially applicable to design for decommissioning of PWRs. The review should also address relevant work undertaken on design for decommissioning during the GDA of other reactor designs in the UK, namely the UK ABWR, UK EPR™ and AP1000®. A key input into the review should also be the RP's own knowledge, skills, experience resources etc. in design for decommissioning and PWR technology.

The scope of design for decommissioning should address: the minimisation of activation and contamination, physical controls to prevent the spread of contamination, features that facilitate decommissioning and reduce radiation doses to decommissioning workers SFAIRP in the future, and measures to minimise the generation of radioactive waste.

The scope of the review excludes the design of nuclear fuel. ONR does not expect the review to address good practices and OEF relating to non-design aspects of decommissioning such as organisational design, operational and decommissioning practices, and decommissioning planning, which are outside the requested scope.

The output of this work will be a written report setting out the good practices and OEF relating to design for decommissioning relevant to NPPs, with focus on PWRs, identified during the review. The report should provide an appropriate summary of the material considered, with clear references. The report should also contain the RP's own commentaries on the overall significance/importance of the OEF considered for a "new", modern PWR design such as the UK HPR1000.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
24 May 2019 Award (award) · 965cbf71-9062-4bbd-9808-a50593914841-291473

more from Health & Safety Executive

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.