Z/2533 The Completion of the Steam Ring Main Link
key details
| Status | active |
|---|---|
| Category (CPV) | 09322000 +2 more |
| Region | Yorkshire and the Humber |
| Deadline | 3 Mar 2017 |
| Contract start | 5 Jun 2017 |
| Contract end | 1 Sept 2017 |
| Procedure | open |
| SME suitable | No |
| OCID | ocds-b5fd17-a3f91409-2594-43d5-abd5-6e0b486ace5a |
description
The works comprise of the completion of the steam and condensate links from the end of the service duct installed from the Charles Morris Header as part of an earlier phase of the project to the Bow Plant Room on the main campus at the University of Leeds, in preparation for the isolation of the steam and condensate distribution system in the vicinity of the former boiler house, which forms part of the University's ICEPS development.
The new links will provide the affected buildings (Earth and Environment, Dobtree, Whetton and Storm Jameson) with supplies of steam and condensate following new connections to the Charles Morris header and Bow Plant Room.
The works include the supply, fabrication, installation, insulation, testing and commissioning of all mechanical pipework, fittings, trap sets etc. together with all associated civils works and builders work in connection with.
All Buildings in the vicinity of the works will remain occupied and in use throughout the duration of the contract.
All existing vehicle and pedestrian accesses are to be maintained throughout the duration of the contract. Any proposed diversions will require prior notification and agreement in advance.
Additional information:
Is a Recurrent Procurement Type? : No
documents
- https://in-tendhost.co.uk/universityofleeds/aspx/ , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/51e7ffdd-067f-484a-b959-e16bdf700a5c , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 13 Feb 2017 | Tender (tender) | · | 51e7ffdd-067f-484a-b959-e16bdf700a5c-130025 |
more from University Of Leeds
- GB-Leeds: PE2025_26-5345 Provision of Christmas Trees, Lights and Associated Works · £25,000 · 1 Jul 2026
- GB-Leeds: PE2026-27_5017 Provision of Student Block Hall Insurance · £100,000 · 30 Jun 2026
- 202526 5916 - research flight services in the Democratic Republic of Congo · £150,000 · 19 Jun 2026
- GB-Leeds: 202526 5793 Cell Disruptor · £50,000 · 21 Apr 2026
- PE2025_26-5843 - Litter picking, bin, external grounds and vehicle cleaning · £30,000 · 1 Apr 2026
- 2024-25/4278a- Supply of a Protein Purification System · £70,000 · 12 Mar 2026
- GB-Leeds: 2025/26-5283- Supply of a High Temperature Simultaneous Thermal Analysis system with MS detector · £500,000 · 4 Dec 2025
- GB-Automated Kjeldahl: Leeds · £100,000 · 1 Dec 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Site Steam Upgrade: Phase 2 Project - Project Management and Detailed Design. · THE PIRBRIGHT INSTITUTE · £80,000
- CA7370 - Design, Installation & Commissioning of Steam Energy Saving · Shropshire Healthcare Procurement Service · £54,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.