Refurbishment and Capital Works Improvement
key details
| Value | £5,011,966 |
|---|---|
| Status | active |
| Category (CPV) | 45214300 |
| Deadline | 13 Oct 2022 |
| Contract start | 6 Jan 2023 |
| Contract end | 30 Sept 2024 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-a3479f9d-0b78-48a3-bd1e-268ef9e6bb7d |
description
Program - Works to be carried out between 9 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].
The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:
Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]
Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.
Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];
Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - First Stage Tender - 09 Sept 2022 - 13 October 2022 [5 weeks]
Adjudication & contractor interviews - 14 October - 3 November 2022 [2 weeks]
Second Stage Tender - 4 November 2022 - 15 December 2022. [6 weeks]
Adjudication & contractor appointment - 15 December - 23 December 2022.
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest
Additional information: Tender packs can be obtained via Craig Pullen (craig@cpconsulting.org.uk)
documents
- https://www.contractsfinder.service.gov.uk/Notice/bbd4ee0f-6fb4-44c9-b66c-0f177e67311b , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 9 Sept 2022 | Tender (tender) | · | bbd4ee0f-6fb4-44c9-b66c-0f177e67311b-570524 |
more from Craig Pullen Consulting
- Isles of Scilly Seabird Recovery Project -Operational Plan · £20,000 · 20 Nov 2024
- Enabling Works Package · £497,620 · 30 Jun 2022
- Infrastructure Installation Services · £242,083 · 7 Jun 2022
- Procurement, Delivery, Building and Installation of Furniture at the South-Central Institute of Technology · £345,000 · 7 Mar 2022
- Audio Visual - Supply of Equipment and Installation Services · £129,246 · 14 Feb 2022
- Procurement of IT Technology equipment for the South-Central Institute of Technology · £130,000 · 4 Feb 2022
- Turbines for the Tidal Industry Energiser Project (TIGER) Interreg Channel Programme · £350,000 · 16 Nov 2021
- IoT South - Bletchley Campus · £10,400,000 · 9 Aug 2021
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- CA17843 - Boston College Summer Refurb · Boston College · £300,000
- Bletchley Campus; Salix Project · Milton Keynes College · £1,400,000
- Brooklands Technical College - New Vickers Building - New Build and Associated External Works · Brooklands Technical College · £11,200,000
- Joe Black Building Heat Pump Design and Construction · University Of Edinburgh · £151,858
- CA12709 - Havering Project · New City College
- Design and Construction of the Housing Innovation & Construction Skills Academy (HICSA). · Sunderland City Council · £13,000,000
- IoT South - Bletchley · Milton Keynes College · £10,400,000
- Enabling Works Package · Craig Pullen Consulting · £497,620
source