Autoclaves Replacement - Pre Construction Services Agreement
key details
| Value | £357,186 |
|---|---|
| Status | complete |
| Category (CPV) | 71530000 |
| Deadline | 7 Apr 2025 |
| Contract start | 9 Apr 2025 |
| Contract end | 30 Sept 2025 |
| Procedure | selective |
| SME suitable | No |
| OCID | ocds-b5fd17-9cd10d61-ff3e-48f0-b339-1bf557ca1fbf |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| BOUYGUES E&S UK LIMITED | £357,186 | 8 Apr 2025 | active |
description
Autoclaves Replacement Pre Construction Services Agreement.
This contract was placed using the Southern Construction Framework 2 stage model, with this contract being stage 1 and including all the relevant design works.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 29 Apr 2025 | Award update (awardUpdate) | · | 9e392f93-cb85-4bcb-bea3-b1e574b98031-842742 |
| 29 Sept 2025 | Award update (awardUpdate) | · | 9e392f93-cb85-4bcb-bea3-b1e574b98031-865879 |
more from Defence Science and Technology Laboratory
- Supply and delivery of Short Wave Infra-Red (SWIR) Laser · £40,050 · 22 Jul 2026
- Forward Asset Service Plan (FASP01) · £15,312,571 · 2 Jul 2026
- Experts Mediazoo · £48,640 · 26 Jun 2026
- Infrastructure and Operations Pathfinder · £49,997 · 28 May 2026
- Maintain and Sustain Services · £8,299,433 · 22 May 2026
- Contract Award Notice for IPMO 1447; RIBA 3-4 deliverables for a new build · £909,234 · 15 May 2026
- Contract Award Notice for IPMO 2109; RIBA 1 deliverables including surveys for a potential refurb · £272,782 · 15 May 2026
- DSTL Service Strategy and Assurance · £41,500 · 6 May 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Main Works EIA Scoping Report · North Wes Anglia NHS Foundation Trust · £34,228
- Cost Consultant Appointment for the Maternity Assessment Unit Capital Scheme · Guy's and St Thomas' NHS Foundation Trust · £177,470
- Gassiott House Student Hub - Project Manager · Guy's and St Thomas' NHS Foundation Trust · £136,553
- Ward Refurbishment Programme - QS · Guy's and St Thomas' NHS Foundation Trust · £76,763
- Ward Refurbishment Programme Procurement Support · Guy's and St Thomas' NHS Foundation Trust · £27,000
- Electrical Consultant for Substations 7 and 8 · Guy's and St Thomas' NHS Foundation Trust · £40,000
- Architect, Albert, Hillyers, Mitchener, Somerset Wards · Guy's and St Thomas' NHS Foundation Trust · £399,453
- Civils and Structure, Albert, Hillyers, Mitchener, Somerset Wards · Guy's and St Thomas' NHS Foundation Trust · £122,474
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.