Anchor Block Removal
key details
| Value | £400,000 |
|---|---|
| Status | active |
| Category (CPV) | 76520000 |
| Region | South West |
| Deadline | 22 Sept 2021 |
| Contract start | 1 Oct 2021 |
| Contract end | 30 Jun 2022 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-9aa78103-18fb-4ee4-92f7-1d05c9d255d8 |
description
Celtic Sea Power is the trading name for Wave Hub Development Services Ltd, a Cornwall Council company.
Celtic Sea Power ("The Vendor") is seeking to remove 6 concrete and steel anchor blocks from the Twin Hub Ltd operated Floating Offshore Wind development site at Hayle in Cornwall, together with all other mooring spread components, as part of the preparation for the future development, construction and operation of a floating offshore wind (FLOW) array.
The Vendor is seeking solutions which;
| • | Ensure the blocks are removed before 30th June 2022 |
| • | Maximise opportunities to remove the blocks before the end of 2021 |
| • | Use the expertise and experience of the successful contractor to maximise value through vessel and operational window choice. |
The anchor blocks were installed in 2014 as foundations for the SeaTricity wave energy device and consist of 6 clump weights, 4 Outer Mooring square clumps at 23 tonnes (dry) / 15 tonnes (wet) and 2 Centre Mooring circular clumps of combined to make a main clump of 126 tonnes (dry) / 80 tonnes (wet).
The vendor is seeking a suitable contractor to:
| • | Develop a methodology for the complete removal of the mooring clumps and residual mooring equipment from the Celtic Sea Power Site by end of June 2022; |
| • | Undertake all HSEQ and Project planning in line with industry standards, |
| • | Supply suitable vessels, plant, craneage, marine spread, ROV's inclusive of fuel, crew, lubes, stores, dues and other disbursements as required to execute the project plan, |
| • | Transport blocks from site, land ashore and dispose of in line with all environmental and waste management legislation, |
| • | Conduct post-removal ROV survey demonstrating that site is clear, |
| • | Provide project plans, HSEQ documentation, daily progress reports, and final report. |
The mooring spread is some 300m or so from the installed electrical infrastructure at the site - which comprises an export cable, hub and 4 x cable tails. A mission critical requirement for the successful contractor will be the minimisation of any potential damage to this infrastructure.
To apply, please download the attached tender documentation and follow instructions therein.
documents
- https://www.contractsfinder.service.gov.uk/Notice/3e54b1a4-5bef-47d7-8071-d7c264b60a25 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/d91ae91a-8553-4b16-a15f-2934774ae64f , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/65dd0c13-f221-4898-8b9e-03c2ce5cc666 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/2815ad5d-8160-4138-b616-4620fd7ab902 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/a068ea63-a857-4e3f-b107-e1b69c648201 , clarifications
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 10 Sept 2021 | Tender amendment (tenderAmendment) | · | 3e54b1a4-5bef-47d7-8071-d7c264b60a25-467832 |
more from WAVE HUB DEVELOPMENT SERVICES LIMITED
- Software Development Services ITT · £40,000 · 10 Dec 2024
- Future Opportunity - Financial Analysis for Renewable Energy Infrastructure Investment · £150,000 · 4 Jul 2024
- Celtic Sea Floating Offshore Wind - Industry Delivery Plans (Logistics and Operational Services) · £36,000 · 3 Jun 2024
- Celtic Sea Floating Offshore Wind - Industry Delivery Plans (Concrete Sub-structures) · £36,000 · 16 May 2024
- Celtic Sea Floating Offshore Wind - Industry Delivery Plans (Inter-array Cables) · £30,000 · 3 May 2024
- Celtic Sea Floating Offshore Wind - Industry Delivery Plans (Anchors & Mooring) · £36,000 · 18 Apr 2024
- Celtic Sea Floating Offshore Wind - Industry Delivery Plans (O&M) · £36,000 · 28 Mar 2024
- Web-based application development and support · £25,000 · 1 Feb 2024
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- THE OWA TALL FLOATING LIDAR SYSTEM TRIAL FOR OFFSHORE WIND DISCRETIONARY PROJECT CONSORTIUM AGREEMENT · The Crown Estate · £105,000
- Celtic Sea Floating Offshore Wind - Industry Delivery Plans (O&M) · CELTIC SEA POWER LIMITED · £36,000
- Sapodilla Bay · UK Hydrographic Office · £23,544
- Gun Bay · UK Hydrographic Office · £22,644
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.