description

The objective of this project is for a formal review and gap analysis to be completed for the documentation, polices, schematics and processes we have created as part of our transition and provide a detailed report to capture and identify gaps and offer guidance on areas of improvement or additional requirement needed.

The key tasks include an independent external supplier to work with the individuals who created and maintain our documentation and procedures, completing a formal onsite review at ORR's head office involving individual and group analysis and review. All required documentation and access will be provided to the identified supplier to assist with the review.

Additional information: Prospective bidders should upload clarification questions and proposals by the dates/times set out in the ITT. Please do not approach any member of the ORR's IT team directly in relation to this project/tender. All correspondence must be through the e tendering portal.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
15 Feb 2018 Award (award) · e8b2d965-c8e4-48ad-ab5c-5bcccb23fa0c-198949

more from OFFICE OF RAIL AND ROAD

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.