A303 Sparkford to Ilchester Surfacing

galliford try Published 10 Mar 2020 Contracts Finder

key details

Statusactive
Category (CPV) 43312000 +2 more
RegionSouth West
Deadline15 Mar 2021
Contract start1 Feb 2022
Contract end1 Sept 2023
Procedureopen
SME suitableNo
OCIDocds-b5fd17-8d3a6832-cae0-4c29-8ff4-2e817560fa30

description

NOTIFICATION OF SURFACING SUBCONTRACT PACKAGE

A303 Sparkford to Ilchester

Galliford Try, as the South West Regional Delivery Partner are delivering the A303 Sparkford to Ilchester dualling project in the county of Somerset on behalf of Highways England. The project involves the design and construction of 5.6km of new dual lane all-purpose carriageway, connecting the existing dual carriageway at the Sparkford and Podimore Bypasses, therefore creating a continuous dual carriageway between Mere and the Podimore Roundabout.

The project is currently awaiting the approval of the Development Consent Order from the Secretary of State for Transport and this is expected to be given in early Spring 2020. Subject to receiving approval, the project is forecast to commence on site in late summer 2020 and will take around 2 years to complete.

Package: Surfacing

We are seeking to appoint a Surfacing Contractor to support the development of the programme, methodology and target price. The successful bidder will also be appointed as Preferred Bidder for the Construction Stage (PCF6), and subject to the agreement of final target price, will deliver the Surfacing for the project without need for any further competition.

Outline Scope of Works

The surfacing works involve the construction of approximately 100,000m2 of new main carriageway and associated interchanges and side roads. A Bill of Quantities is provided along with layout drawings. The majority of the new A303 dual carriageway sits to the north of the existing A303 however the new and existing carriageways cross at approx. ch3300 & ch3750 which will result in some temporary surfacing works.

Programme

The construction programme is still under development. The initial surfacing works will involve the construction of Steat Hill Link and Downhead Junction Link with surfacing taking place in early 2021. The main carriageway surfacing is expected to take place during 2022. Tenderers should allow for 12 machine visits and 8 footpath / handlay visits. The surfacing works will be constructed within normal working hours with the exception of the tie ins and crossing points on the A303 which are likely to be undertaken during night time working. Extra Over costs for night time working should be clearly identified.

Bidders are invited to propose any areas of innovation that may offer benefits to the project including price, programme and quality and these will be taken into consideration when selecting the Preferred Bidder.

Timings

Deadline for Notifications of Interest17:30hrs Monday 16th March 2020
Deadline for tender submission17:30hrs Monday 23rd March 2020

If this package is of interest to your company please contact the Managing QS [Adrian Paddock] by e-mail on adrian.paddock@gallifordtry.co.uk, by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

Additional information: NOTIFICATION OF SURFACING SUBCONTRACT PACKAGE

A303 Sparkford to Ilchester

Galliford Try, as the South West Regional Delivery Partner are delivering the A303 Sparkford to Ilchester dualling project in the county of Somerset on behalf of Highways England. The project involves the design and construction of 5.6km of new dual lane all-purpose carriageway, connecting the existing dual carriageway at the Sparkford and Podimore Bypasses, therefore creating a continuous dual carriageway between Mere and the Podimore Roundabout.

The project is currently awaiting the approval of the Development Consent Order from the Secretary of State for Transport and this is expected to be given in early Spring 2020. Subject to receiving approval, the project is forecast to commence on site in late summer 2020 and will take around 2 years to complete.

Package: Surfacing

We are seeking to appoint a Surfacing Contractor to support the development of the programme, methodology and target price. The successful bidder will also be appointed as Preferred Bidder for the Construction Stage (PCF6), and subject to the agreement of final target price, will deliver the Surfacing for the project without need for any further competition.

Outline Scope of Works

The surfacing works involve the construction of approximately 100,000m2 of new main carriageway and associated interchanges and side roads. A Bill of Quantities is provided along with layout drawings. The majority of the new A303 dual carriageway sits to the north of the existing A303 however the new and existing carriageways cross at approx. ch3300 & ch3750 which will result in some temporary surfacing works.

Programme

The construction programme is still under development. The initial surfacing works will involve the construction of Steat Hill Link and Downhead Junction Link with surfacing taking place in early 2021. The main carriageway surfacing is expected to take place during 2022. Tenderers should allow for 12 machine visits and 8 footpath / handlay visits. The surfacing works will be constructed within normal working hours with the exception of the tie ins and crossing points on the A303 which are likely to be undertaken during night time working. Extra Over costs for night time working should be clearly identified.

Bidders are invited to propose any areas of innovation that may offer benefits to the project including price, programme and quality and these will be taken into consideration when selecting the Preferred Bidder.

Timings

Deadline for Notifications of Interest17:30hrs Monday 16th March 2020
Deadline for tender submission17:30hrs Monday 23rd March 2020

If this package is of interest to your company please contact the Managing QS [Adrian Paddock] by e-mail on adrian.paddock@gallifordtry.co.uk, by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
18 Mar 2021 Tender amendment (tenderAmendment) · 053ab7bf-987f-40f2-a32b-841c1d47526b-421189

more from galliford try

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.