GB-Edinburgh: Fabrication of Solar Array, A-Frames and Pedestals - Hyskeir
key details
| Value | £137,728 |
|---|---|
| Status | complete |
| Category (CPV) | 45255400 |
| Region | Scotland |
| Deadline | 15 Jan 2024 |
| Contract start | 16 Jan 2024 |
| Contract end | 15 Mar 2024 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-bbf4a110-2419-4260-9ffa-501d45d93b32 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| JGC Engineering and Technical Services Ltd | £137,728 | 15 Jan 2024 | active |
description
Specification of Requirements
Solar Array and A-Frames:
Fabricate 6.4m high x 12m x 4m aluminium framework with access ladders leading to A-frames on two working platforms finished with a GRP deck and handrail as detailed on NLB contract drawings.
Pedestals:
Fabricate two number aluminium pedestals to support the Racon monitoring system and two number aluminium pedestals to support the LED Optics as detailed on NLB contract drawings.
General:
On completion of the fabrication works, a trial assembly is to be carried out at the suppliers premises to allow the Project Leader and / or his representative the opportunity to inspect individual structural members for acceptability, to check the proposed sequence of erection for safety, and to measure the expected duration of operations on site.
Following the trial assembly the supplier should dismantle the structures, then schedule and co-ordinate the delivery and transportation of all components and other commodities to NLB (Oban) Base prior to Friday 15 March 2024.
Programme
All tenderers must submit a manufacturing and production plan , at tender stage, with a proposed start date during the week commencing Monday 15 January 2024. It is proposed that the fabrication works should take place over a period of 8-10 weeks and delivery of all items within the bill of quantities must be made to NLB's depot in Oban before Friday 15 March 2024.
Tenderers should also advise of any anticipated delays or advancement of the fabrication works programme and incorporate all relevant lead-in times for materials, proprietary items, etc.
The tenderers programme shall clearly set out the sequence of fabrication and proposed time limit within each operation giving the dates of commencement and completion. The tenderer in preparation of this programme shall take cognisance of work by sub-contractors, and availability of materials, transportation and all other matters related to the works. On agreement or negotiation of the programme by the Project Leader, the tenderer will be responsible for the execution of the work in conformity therewith.
Submission of the programme will not relieve the tenderer of his responsibility to apply in writing for instructions, drawings etc. in accordance with the agreed contract terms and conditions. The tenderer shall record progress on a copy of the programme kept on his premises. The tenderer must also update or redraft the programme without delay if any circumstances arise, which affect the progress of the works and submit copies of all revisions to the Project Leader immediately.
For a more detailed description please refer to the Tender Document.
Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
documents
- https://www.contractsfinder.service.gov.uk/Notice/c6d0bdd9-d04d-4464-aef4-45160c118953 , tenderNotice
- https://www.delta-esourcing.com/tenders/UK-GB-Edinburgh:-Fabrication-of-Solar-Array,-A-Frames-and-Pedestals---Hyskeir/75V8858U9V , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 21 Nov 2023 | Tender (tender) | · | c6d0bdd9-d04d-4464-aef4-45160c118953-700546 |
| 16 Jan 2024 | Award (award) | · | 9c66f9af-7ea6-4c43-b5ef-3fc880744e55-714532 |
more from Northern Lighthouse Board
- Provision of Corporate Workwear · 17 Apr 2026
- ICT Laptop purchase · 3 Feb 2026
- GB-Edinburgh: Cyber Security testing services and Incident response · £77,200 · 25 Apr 2025
- GB-Edinburgh: Buoy Bodies · £50,000 · 19 Mar 2025
- GB-Edinburgh: Autodesk Subscription Renewal · £50,000 · 10 Mar 2025
- GB-Edinburgh: Refurbishment and Redecoration of Lady Isle Lighthouse · £500,000 · 21 Feb 2025
- GB-Edinburgh: Stevenson Rooms VC Upgrade · £50,000 · 21 Feb 2025
- TENDER FOR THE PROVISION OF MARINE SOLAR PANELS FOR THE GENERAL LIGHTHOUSE AUTHORITIES OF THE UNITED KINGDOM AND IRELAND · £900,000 · 21 Feb 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- The supply of Mechanical Fitting, Fabrication and Welding Services · THE FELIXSTOWE DOCK AND RAILWAY COMPANY · £1,250,000
- HNL - AOMR - Gauging Station Platforms · Environment Agency · £94,350
- Design, Supply, and Installation of a Liquid Nitrogen Storage &Distribution System · UK Atomic Energy Authority · £1,000,000
- Fabrication Services · Scottish Water
- Major Refurbishment of Port Ellen Lighthouse · Northern Lighthouse Board · £150,000
- Early Legacy 3m3 Boxes - Liners & AFP's (CALL OFF - ITT) - Work package 12 · Sellafield Ltd · £4,799,680
- CA16398 - RFQ 2025/17 - Provision of Additional Steps and Fall Restraint Rails to Council Fleet · Newry, Mourne and Down District Council (NMD)
- Barry Island Changing Rooms for the Vale Of Glamorgan Council · Vale of Glamorgan Council
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.