gvtcx

Reinforced Earth SubContract Enquiry for A303 Sparkford to Ilchester

galliford try Published 5 Mar 2020 Contracts Finder

key details

Statusactive
Category (CPV) 45262620
Deadline24 Mar 2021
Contract start1 Sept 2021
Contract end1 May 2022
Procedureopen
SME suitableNo
OCIDocds-b5fd17-0c7e5760-67ba-4cc0-9dec-4331aca74bf4

description

NOTIFICATION OF REINFORCED EARTH SUBCONTRACT PACKAGE

A303 Sparkford to Ilchester

Galliford Try, as the South West Regional Delivery Partner are delivering the A303 Sparkford to Ilchester dualling project in the county of Somerset on behalf of Highways England. The project involves the design and construction of 5.6km of new dual lane all-purpose carriageway, connecting the existing dual carriageway at the Sparkford and Podimore Bypasses, therefore creating a continuous dual carriageway between Mere and the Podimore Roundabout.

The project is currently awaiting the approval of the Development Consent Order from the Secretary of State for Transport and this is expected to be given in early Spring 2020. Subject to receiving approval, the project is forecast to commence on site in late summer 2020 and will take around 2 years to complete.

Package: Reinforced Earth Design & Supply

We are seeking to procure a supplier to support the design process alongside our designer Sweco and supply the reinforced soil components and concrete face panels.

Outline Scope of Works

The project involves the construction of two bridges which are both to be constructed with reinforced soil abutments and wingwalls with concrete facing panels.

Hazelgrove Bridge - single span bridge carrying the new A303 dual carriageway over a new single carriageway link road

Steat Hill Bridge - single span bridge carrying a link road over the new A303 dual carriageway

Programme

Design works is ongoing on the project and we are seeking to complete the design to both bridges in Spring 2020. Construction works on both bridges will commence in late summer/autumn 2020 with completion in Spring 2021.

Timings

Deadline for Notifications of Interest17:30hrs Wednesday 12th March 2020
Deadline for tender submission17:30hrs Wednesday 18th March 2020

If this package is of interest to your company please contact the Managing QS [Adrian Paddock] by e-mail on adrian.paddock@gallifordtry.co.uk, by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

Additional information: NOTIFICATION OF REINFORCED EARTH SUBCONTRACT PACKAGE

A303 Sparkford to Ilchester

Galliford Try, as the South West Regional Delivery Partner are delivering the A303 Sparkford to Ilchester dualling project in the county of Somerset on behalf of Highways England. The project involves the design and construction of 5.6km of new dual lane all-purpose carriageway, connecting the existing dual carriageway at the Sparkford and Podimore Bypasses, therefore creating a continuous dual carriageway between Mere and the Podimore Roundabout.

The project is currently awaiting the approval of the Development Consent Order from the Secretary of State for Transport and this is expected to be given in early Spring 2020. Subject to receiving approval, the project is forecast to commence on site in late summer 2020 and will take around 2 years to complete.

Package: Reinforced Earth Design & Supply

We are seeking to procure a supplier to support the design process alongside our designer Sweco and supply the reinforced soil components and concrete face panels.

Outline Scope of Works

The project involves the construction of two bridges which are both to be constructed with reinforced soil abutments and wingwalls with concrete facing panels.

Hazelgrove Bridge - single span bridge carrying the new A303 dual carriageway over a new single carriageway link road

Steat Hill Bridge - single span bridge carrying a link road over the new A303 dual carriageway

Programme

Design works is ongoing on the project and we are seeking to complete the design to both bridges in Spring 2020. Construction works on both bridges will commence in late summer/autumn 2020 with completion in Spring 2021.

Timings

Deadline for Notifications of Interest17:30hrs Wednesday 12th March 2020
Deadline for tender submission17:30hrs Wednesday 18th March 2020

If this package is of interest to your company please contact the Managing QS [Adrian Paddock] by e-mail on adrian.paddock@gallifordtry.co.uk, by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
18 Mar 2021 Tender amendment (tenderAmendment) · 62edba2a-20ba-4273-b48c-1e6684b2c77a-421122

more from galliford try

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.