key details

Value£1
Statuscomplete
Category (CPV) 45262670
RegionLondon
Deadline10 Feb 2020
Contract start13 Feb 2020
Contract end24 Feb 2020
Procedureopen
SME suitableNo
OCIDocds-b5fd17-75c49e4a-0c4c-48e3-afab-e7323bb86ca1

Award

SupplierValueDateStatus
not named £12,191 13 Feb 2020 active

description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.

The Project comprises:

  • a.tunnels:
  • i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
  • ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
  • b.Worksites:
  • i.five main tunnel Worksites (drive and/or reception sites)
  • ii.16 CSO Worksites
  • iii.two System modification Worksites Thames Tideway Tunnel
  • iv.works at Beckton Sewage Treatment works.

Section 4: Scope of Works

Supply only of 4no. Bulkheads highlighted in red the overhead drawing no.3350-BAMNU-HAMPS-450-CZ-DR- 200027

Hammersmith site has requirement for bulkheads that will close openings that have been cast into Wall A. Their primary function is to protect the Chamber as the Inlet Channel breaks through into the new structure. The rubber gaskets create a watertight seal to stop inlet channel sewage from entering the chamber, delaying its use as a live sewer and therefore maintaining a working environment that does not need monitoring or confined space procedures.

Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.

Quotations will be evaluated based on;

Cost

Timeliness of return

Adherence to and demonstration of understanding of the drawings and specifications provided at this point.

Provision of accurate product specifications to accompany the quotation.

Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.

Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail.

BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)

Hammersmith Site

Additional information: Hammersmith Site

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
8 Jan 2021 Award (award) · b0bce49f-0a82-4434-b528-3207f8277a31-404436

more from BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.