Stour Culvert (0182) Major Maintenance works 2020 (Re-waterproofing)

Wigan Council Published 6 Aug 2020 Contracts Finder

key details

Value£80,000
Statusactive
Category (CPV) 45200000
RegionNorth West
Deadline4 Sept 2020
Contract start14 Sept 2020
Contract end18 Oct 2020
Procedureopen
SME suitableYes
OCIDocds-b5fd17-711451fc-0b51-4bd5-a917-f13ad98c760e

description

Stour Culvert is an insitu reinforced concrete box structure. The culvert carries Stour Road over the Ellenor Brook watercourse. There is a single carriageway over the bridge for one lane of traffic in each direction.

The works will comprise of excavation of road surfacing and fill material, removal of existing paving slabs, removal of existing waterproofing system to expose the concrete deck, preparation of concrete deck and application of new waterproofing system. This will be followed by reinstatement works including carriageway and footway surfacing, lining and kerbs where necessary.

Additional information:

Re-waterproofing

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
6 Aug 2020 Tender (tender) · a906515f-6874-4fee-92e5-0df21c14070e-374497

more from Wigan Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.