HVLV Replacement Project
key details
| Value | £1,200,000 |
|---|---|
| Status | active |
| Category (CPV) | 09310000 +5 more |
| Region | London |
| Deadline | 31 Jul 2020 |
| Contract start | 1 Dec 2020 |
| Contract end | 1 Jun 2021 |
| Procedure | selective |
| SME suitable | No |
| OCID | ocds-b5fd17-6b60e0c6-92ac-410b-a340-c58291f180f4 |
description
This is the first stage of a two stage tender process.
The Science Museum have identified the need to replace key components of their main electrical infrastructure supplying their South Kensington premises.
The building is supplied at Medium Voltage (MV) through a 6.6kV private network originating from two feeders originating at the neighbouring Natural History Museum site. The MV distribution supports five load centres distributed around the basement of the Science Museum. The load centres are denoted as substations H, J, K, L & M. Load centre H, J, K & M each include:
| - | 2 No 800kVA transformers, each with close-coupled ring main units. |
| - | 2 No LV switchpanels, each fed from a dedicated transformer. |
The two LV switchpanels in each load centre are linked via a busbar interconnector, which is protected by an air circuit breaker (ACB) at either end of the connection. In all load centres the transformers and LV switchgear are located in separate rooms
Load centre L utilises a single transformer/RMU and single switchpanel arrangement.
The ring main units on site are generally manufactured by Brush and are the Falcon Beta model; however there are a limited quantity of Merlin Gerin Ringmaster units installed.
The transformers were either manufactured by Brush, Peebles or Schneider.
The LV switchgear was generally manufactured by Rees Switchgear and comprises GEC switch-fuse outgoing ways and GEC M-Pact ACB incomers and bus-interconnector protective devices.
Much of the distribution equipment is life-expired, is no longer supported by the original equipment manufacturers and has been identified as requiring replacement.
This project involves the replacement of RMUs and ACBs in substations H, J, L & M. The replacement/upgrade project will be undertaken in a phased manner that causes no business disruption to the Science Museum. This will require much of the works to be undertaken outside or normal working hours, during the evenings or weekends.
The Science Museum's MV and LV maintenance is carried out by an on-site FM provider. All works will need to be undertaken in collaboration with the on-site team.
documents
- https://www.contractsfinder.service.gov.uk/Notice/98a1c0f2-866c-4db3-8da1-eee1b7a6f18c , tenderNotice
- https://www.mytenders.co.uk/search/show/search_view.aspx?ID=JUL160108 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 20 Jul 2020 | Tender (tender) | · | 98a1c0f2-866c-4db3-8da1-eee1b7a6f18c-371502 |
more from Science Museum Group
- SIM Architect and Lead Designer for Wonderlab and Power Up - AWARD · 2 Dec 2025
- Flight Gallery Improvements - Graphics - AWARD · 1 Oct 2025
- ScM Flight Gallery - Lighting Upgrades - AWARD · 1 Oct 2025
- Locomotion Exit Surveys 2024-27 - AWARD · 23 Sept 2025
- NRM Building Regulations Principal Designer - AWARD · 27 Aug 2025
- NCC Consolidation Project: Manufacture and Supply of 200 Large Pallets - AWARD · 21 Aug 2025
- Disassembly and Removal of Existing Pallet Racking and Manufacture and Installation of Adjustable Pallet Racking in Hangar L1 - AWARD · 21 Aug 2025
- Horizons Gallery Graphic Designer - AWARD · 20 Aug 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Purchasing of Energy · Liverpool Experience Campus Ltd · £11,852,500
- The Sigma Trust - Electricity · The Sigma Trust
- BMAT Education Trust – Gas & Electricity Supply Services 2026 · BMAT Education Trust · £5,400,000
- The Sigma Trust - Electricity Supply · The Sigma Trust
- Electricity - LEO Academy Trust · LEO Academy Trust
- Hedingham School and Sixth From - Electricity Dynamic Market · Hedingham School and Sixth Form
- Impact Multi Academy Trust - Electricity · Impact Multi Academy Trust
- Blessed Edward Bamber Catholic Multi-Academy Trust - Electricity 2026 · Blessed Edward Bamber Catholic Multi-Academy Trust
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.