key details

Value£2,462,700
Statuscomplete
Category (CPV) 45000000
Deadline13 Jul 2020
Contract start6 Jan 2021
Contract end18 Jun 2021
Procedureselective
SME suitableYes
OCIDocds-b5fd17-67009e92-ae47-4134-ad11-a1508eeda061

Award

SupplierValueDateStatus
BALFOUR BEATTY KILPATRICK LIMITED £2,462,700 16 Nov 2020 active

description

The University of Manchester has appointed a contractor to perform the fit out works to the sixth floor at the Henry Royce Institute Hub Building at the University of Manchester. The project will be part funded by the European Regional Development Fund (ERDF - https://www.gov.uk/guidance/england-2014-to-2020-european-structural-and-investment-funds).

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
18 Jun 2020 Tender amendment (tenderAmendment) · 50224dba-8b60-46b4-81f2-a698f2a701f5-365016
5 Jan 2021 Award (award) · 15c22e59-a0d4-44ab-9709-92418a689368-398584

more from UNIVERSITY OF MANCHESTER

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.