The Coal Authority Published 3 Jul 2024 Find a Tender

key details

Value£800,000
Statusplanned
Category (CPV) 76530000
RegionYorkshire and the Humber
OCIDocds-h6vhtk-047a32

description

The Coal Authority (Client) was established by Parliament to undertake specific statutory duties, set out in the Coal Industry Act 1994, associated with licensing coal mining operations; managing property and the historic legacy arising from the ownership of the coal reserves and underground workings; settling subsidence damage claims not falling on coal mine operators and providing access to coal mining information.

  1. Background

The mine water in the Barnsley-Manvers-Grimethorpe mine water block is thought to be rising.

Recovered mine water in this area represents a potential risk to the overlying Permian aquifer, as well as surface water in the area. To assess the mine water regime, and inform future mine water management strategies, a borehole is required that would target the Brodsworth or Bullcroft colliery mine workings.

Therefore, the Coal Authority (CA) requires a mine water monitoring borehole to increase the monitoring infrastructure in the area. The data from this borehole will be used to improve understanding of mine water in the Barnsley-Manvers-Grimethorpe mine water block, through water level monitoring and quality sampling.

  1. Delivery

The CA look to collaboratively engage with landowners to obtain access and a licence to carry out the drilling works. It should be noted that this engagement may take up to a maximum of 15 months, from initial point of contact however, in some cases this is significantly less.

With this in mind, the Invitation to Tender is sent out part-way through this timeframe. Nevertheless, and to avoid any delays, the Contract will be awarded with a Contract Award Date and Start Date as two different dates.

  1. Engagement Opportunities

The CA are always looking for ways to improve and streamline projects.

Due to the defined verticality requirements, it is envisaged that the most robust and reliable method of completing the mine water monitoring boreholes is by drilling a pilot hole using a wireline coring system, followed by reaming to the required diameter(s).

However, the CA would welcome your feedback on this including any other methods that may be deemed more suitable to guaranteeing verticality such as directional drilling.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
3 Jul 2024 Prior information notice (F01) Earlier regulations 020287-2024
3 Jul 2024 Planning (planning) · 7e806cee-5f69-492d-9054-56d520e4c0fb-763936