A417 Missing Link - Concrete Surface Water Channel & Concrete Safety Barrier

KIER TRANSPORTATION LIMITED Published 20 Dec 2024 Contracts Finder

key details

Value£1,250,000
Statuscomplete
Category (CPV) 45000000
RegionSouth West
Deadline31 Jan 2025
Contract start12 May 2025
Contract end3 Feb 2027
Procedureselective
SME suitableNo
OCIDocds-b5fd17-0846583d-9558-436e-9c2b-c87224c67c1f

Award

SupplierValueDateStatus
Extrudakerb (Maltby Engineering) Limited £1,680,007 15 May 2025 active

description

Purpose of Notice -

The procurement of a Subcontractor for the A417 Missing Link - Concrete Surface Water Channel & Concrete Safety Barrier works in connection with the A417 Missing Link at Air Balloon.

Scheme Description -

Under the National Highways Limited Regional Delivery Partnership (RDP), we are appointed as the Principal Contractor for the design and construction of a new dual carriageway at the A417 Missing Link at Air Balloon.

The scheme would provide 3.4 miles (5.5km) of new, rural all-purpose dual carriageway for the A417. The new dual carriageway would connect the existing A417 Brockworth bypass with the existing dual carriageway A417 south of Cowley.

Registering Interest -

Interested parties are to register their interest through making contact via guy.hornsey@kier.co.uk.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
20 Dec 2024 Tender (tender) · d886258d-a40e-4c9c-b536-6dfe0abc0e5f-812802
29 Oct 2025 Award (award) · ea6732f3-5f5c-4c03-a9d7-65ae9b24baa4-870125

more from KIER TRANSPORTATION LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.