Kedleston Rd, Boiler Replacement and CHP
key details
| Status | active |
|---|---|
| Category (CPV) | 42160000 +3 more |
| Region | East Midlands |
| Deadline | 1 May 2015 |
| Contract start | 18 May 2015 |
| Contract end | 2 Nov 2015 |
| Procedure | open |
| SME suitable | No |
| OCID | ocds-b5fd17-4cbe79fe-adc8-11e6-9901-0019b9f3037b |
description
The Services Contractor shall supply, install, test and commission the installations as detailed on the Tender drawings and within this specification, employing skilled personnel and specialist contractors as necessary to achieve the standards described.
The works include the supply, installation, testing and commissioning of new replacement boilers, builders work, CHP, chiller, BMS controls, back up HWS generation, new replacement pumps, new pipework and associated mechanical and electrical services within the East Tower and North Tower plantrooms at the University of Derby, Kedleston Road Campus in Derby.
The works shall also include the isolation, de-commissioning, strip-out and removal from site of the existing boiler plant, chiller, pumps, pipework control wiring and associated installations made redundant by the replacement boiler/chp/chiller installation.
The Mechanical Contractor shall supply, install, test and commission the installations as detailed on the Tender drawings and within this Specification, employing skilled personnel and specialist contractors as necessary to achieve the standards described. The works are to be carried out two phases, Phase 1 to provide direct gas fired HWS generation to cover the summer period and when commissioned and operational to remove the existing boiler plant, controls, pipework pumps and Install new boiler plant pipework, pumps, controls, pipework and chillers before 1st September 2015. Phase 2 to de commission the R22 chiller and remove, install the new CHP, complete the chilled water system and commission and then complete and commission the CHP by the 2nd November 2015.
Contract is to be MF/1
All of works are to be carried out to the agreed programme and completed by 02/11/15.
The project shall be phased to ensure minimum disruption is caused on site.
The contract intended programme requirements are appended to this section of the Specification.
Date for Commencement of the works (to allow plant lead-in periods): 11/05/15
Date for start on site: 11/05/15
Date for Completion Phase 1: 31/08/15
Date for start of Phase 2: 14/09/15
Date for Completion Phase 2: 02/11/15
The Services Contractor will be required to prepare a master programme and progress chart to clearly indicate how the work is to be carried out to completion within the period of the Contract.
To arrange a site visit please contact Ian Cain on 01332 591104 or i.cain@derby.ac.uk or Martin Simms on 01332 591107 or m.simms@derby.ac.uk
Additional information: Is a Recurrent Procurement Type? : No https://in-tendhost.co.uk/derby/aspx/
documents
- https://in-tendhost.co.uk/derby/aspx/ , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/18cf4861-d81c-4c2e-b312-eceed55ede9b , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 13 Apr 2015 | Tender (tender) | · | ocds-b5fd17-4cbe79fe-adc8-11e6-9901-0019b9f3037b-62397-krboiler-icc-2015 |
more from University of Derby
- ANPR Car Park Management System (hardware and software) - Prior Information Notice PIN · 21 Feb 2025
- Sustainable Energy Infrastructure · 1 Feb 2023
- India Consultancy · £400,000 · 7 Jun 2022
- Internal & External Audit Services · £1,900,000 · 5 Apr 2022
- Payment Processing Agents · 25 Mar 2022
- Mechanical & Electrical Goods and Services · £4,000,000 · 4 Jan 2022
- Occupational Health Services for Students · 22 Sept 2021
- Servicing & Maintenance of CCTV, Door access, Barriers and Automatic Doors · 2 Sept 2021
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Hylands House Boiler Replacement Works · Chelmsford City Council · £220,000
- Yew Tree Community School - Boilers and BMS Panel Replacement (Five of five school summer shutdown projects) · Oldham Metropolitan Borough Council · £90,000
- Woodhouses Voluntary Controlled Primary School - Boilers and BMS Panel Replacement (Four of five school summer shutdown projects) · Oldham Metropolitan Borough Council · £130,000
- Limehurst Community Primary School - Boilers and BMS Panel Replacement (Three of five school summer shutdown projects) · Oldham Metropolitan Borough Council · £200,000
- Burnley Brow Community Primary School - Boilers and BMS Panel Replacement (Two of five school summer shutdown projects) · Oldham Metropolitan Borough Council · £140,000
- Beever Primary School - Boilers and BMS Panel Replacement (One of five school summer shutdown projects) · Oldham Metropolitan Borough Council · £390,000
- NCC1771 County Hall Main Boilers Replacement · Northumberland County Council · £450,000
- UOW989 Woodbury Building Boiler Replacement - AWARD · University Of Worcester · £145,850
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.