gvtcx

For the provision of Design, Remediation and Construction Works for Barrow Waterfront, Barrow

Westmorland and Furness Council Published 16 Jul 2024 Contracts Finder

key details

Value£16,000,000
Statuscomplete
Category (CPV) 45000000
RegionNorth West
Deadline1 May 2024
Procedureopen
OCIDocds-h6vhtk-044d6d

Award

SupplierValueDateStatus
Redstart Northwest Limited · · active

description

This Tender concerns Phase Two of Marina Village. The Council wishes to appoint a design and build contractor to remediate the site to broadly the same standard as Phase 1 and to install some associated enabling infrastructure on the site to assist future housing suppliers to develop the site for 808 homes (Phase 1 and Phase 2 together). Please refer to the Scope for further information.

Contractual Context

  • (a)This ITT is for a two staged procurement to identify a Contractor to undertake the Works identified in the Schedule 2 (Scope relating to the design and remediation/construction of the Barrow Waterfront Phase Two site in Barrow, Cumbria).
  • (b)The 2 stages are:
  • Stage 1: Design Services (including, but not limited to surveys, investigations, reporting, planning, communications and costings) within an NEC4 Option A Engineering and Construction Contract (ECC).
  • Stage 2: Construction Works (delivery of the remediation strategy and infrastructure designs as agreed at the end of Stage 1) within an NEC4 Option A Engineering and Construction Contract (ECC).
  • (c)For Stage 1, the Contractor will enter into a NEC4 Option A Engineering and Construction Contract (ECC) with the Council (Client) and undertake the services outlined in the Scope.
  • (d)The Contractor will, as part of the Scope of Stage 1, undertake any necessary supplementary investigations, studies, assessments, etc., produce all drawings and specification for the works; and secure all necessary consents and approvals. The Contractor will, among other things, provide a pre-construction information (PCI) document as well as an updated priced activity schedule for discussion and acceptance at the end of Stage 1. For further Details please refer to the Scope.
  • (e)If the Client accepts the Stage 1 design and price, the Contractor will be asked to provide the Stage 2 works by entering into a Stage 2 Engineering and Construction Contract with the Client.
  • (f)For the avoidance of doubt, the initial contract will be for the provision of Stage 1 only. The Client has no contractual obligation to commit to entering into the Stage 2 Engineering and Construction Contract and at its sole discretion may seek to end or reprocure the project at the end of Stage 1.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

3 notices published against this procurement.

PublishedTypeRegimeNotice
27 Mar 2024 Contract notice (F02) Earlier regulations 009987-2024
27 Mar 2024 Tender (tender) · ed0263d2-178a-40e7-bcd2-1794965e9e75-735797
16 Jul 2024 Contract award notice (F03) Earlier regulations 021809-2024

more from Westmorland and Furness Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.