Storage Evidence for the Dynamic Dispatch Model
key details
| Value | £40,000 |
|---|---|
| Status | complete |
| Category (CPV) | 73000000 |
| Deadline | 25 Jan 2018 |
| Contract start | 5 Feb 2018 |
| Contract end | 31 Mar 2018 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-43147aba-ee26-41a2-a2bc-a6cdbc2610df |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Mott Macdonald | £36,277 | 2 Feb 2018 | active |
description
BEIS wishes to procure robust technical and cost assumptions for a representative set of electricity storage technologies out to 2050 for its Dynamic Dispatch Model. Other key deliverables are the QA & assumptions logs, underlying data/analysis plus methodology and publishable summary reports.
Contractors are invited to set out their proposed methodology on how to derive a robust and consistent set of technical and cost assumptions for different types of electricity storage technologies that have been and are likely to be deployed between 2010 -2050. Contractors need to ensure that these assumptions can be easily updated in the future. These assumptions will feed in to BEIS's Dynamic Dispatch Model. BEIS specifically wishes to procure the following information:
- A set of assumptions for an agreed number of electricity storage 'types':
The contractor is expected to summarise all of the possible electricity storage technologies (including key attributes e.g. technical/cost/primary use, etc.) that they consider may be in scope and provide a justification as to why they are considered to be in scope. The contractor will then be expected to make a recommendation on how to create a set of representative electricity storage types that BEIS can use in its modelling (covering the period from 2010 to 2050). BEIS envisages around five technologies or "proxy technologies" if the evidence suggests that some technologies could be grouped together given their similarities.
- Technical input assumptions for the agreed types of electricity storage:
BEIS wishes to procure robust technical reference parameters for electricity storage technology types commissioning from 2010 to 2050. The indicative list of the type of technical assumptions that are being sought is as follows: Plant capacities, durations, energy/capacity ratios, round trip efficiencies, life cycles, charge/discharge profiles, degradation profiles, annual build limits and construction time.
- Cost input assumptions for the agreed types of electricity storage technologies:
BEIS wishes to procure (high, medium, low) cost profiles for different types of electricity storage technologies from 2010 to 2050. The indicative list of the type of cost assumptions that are being sought is as follows: Pre-development costs, construction costs and operational costs.
- A tool which allows costs to be adjusted over time to cover the period 2010-2050:
BEIS wishes to procure a tool which will enable the cost profiles to be updated over time. This might include experience curves and indexes to relevant sources on deployment/prices.
The key deliverables expected from this project are: QA and assumptions logs, underlying data/evidence/analysis, spreadsheets with the final cost and technical assumptions, a spreadsheet tool, a methodology report and a publishable summary report on the final electricity storage assumptions.
Additional information: How to Apply:
If you wish to take part in this procurement, please see the attached Tender documents attached to this Notice and send your completed Proposal to Pamela Howie and Nazish Choudery at the e-mail addresses stipulated in the "Who to Contact" section and in the ITT.
Please note that Section E 'Terms and conditions applying to this Invitation to Tender' (page 6) of the ITT document was updated on 18/01/2018. Please also be aware that completing Section 8.1 of the Standard Selection Questionnaire included as part of the ITT is not compulsory. See the Q&A log in 'Attachments' above for further information.
Any late submissions will not be considered. BEIS reserves the right to halt the procurement process and to not award a contract. BEIS will not be held liable for the recovery of costs from unsuccessful bids if a contract is not awarded. All costs will be borne by the bidding organisations. If a contract is created it will be upon BEIS Standard Terms and Conditions which are available on Contracts Finder with this notice.
Completed tender submissions must be returned by e-mail to BEIS, to the e-mail addresses given in this advertisement (Pamela.Howie@beis.gov.uk and Nazish.Choudery@beis.gov.uk) by 11am on 25th January 2017. After reviewing and evaluating the written proposals, BEIS may decide to hold bid clarification meetings with suppliers. If successful and upon contract signature, the supplier is expected to attend a kick-off meeting taking place on 5th February 2018 (or shortly thereafter). Project completion is required by 31st March 2018.
documents
- https://www.contractsfinder.service.gov.uk/Notice/246a7cd7-8afc-4f8a-9e76-892eb169ec9e , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/a15dce8a-9940-4887-aa5a-6266ec9c2ad9 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/a3b9c991-d6bb-48a0-a5b0-ec53d297f0f7 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/119ab4ba-3711-4fd9-92fb-ffbe40e6debc , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/3382e586-e2e1-43a0-8587-7d1ee6c46ff0 , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/73c0a0ca-25c3-4e80-bd3f-036ea750df8f , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/b0671c6a-93b7-4f48-85bf-8ac904337ebc , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/ca9e539c-f342-47ae-bba1-2566258d777a , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/8e297b8b-504a-4478-843a-3d90a51f6915 , biddingDocuments
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 2 May 2018 | Award (award) | · | 136dfb95-b893-4cdb-9ca2-29779173da49-214058 |
more from Business Energy and Industrial Strategy
- Delivery Partner 2 (DP2) - WH:SHF and WH:LG · 11 Sept 2025
- Heat Network Efficiency Scheme - HNES MAIN · £2,961,208 · 5 Nov 2024
- Re-procurement of Hydrogen Legal Advisors · 1 May 2024
- Technical Assistance Facility 2 - Pre-Tender Market Engagement · 14 Aug 2023
- APGB Reprocurement - Suppliers Event · 6 Jul 2023
- Medicines Manufacturing Skills and Training Consultation · 21 Apr 2023
- Sizewell C Legal Services Contract · £7,500,000 · 31 Mar 2023
- Local Authority 'Capability' and 'Capacity' Building Grant Funding Pilot Evaluation · 9 Feb 2023
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- CST295 Pension Fund Address Tracing · Derbyshire County Council · £70,000
- HMRC Annual Stakeholder Research 2024-2026 · H M REVENUE & CUSTOMS · £226,000
- project_9401 - LLE Evaluation · Department for Education · £974,948
- BBC Charter Review Commercial Funding Options · Department for Culture, Media and Sport · £196,300
- NDA9/00916.091 - Support to Sealed sources landscape Review · Nuclear Decommissioning Authority · £80,000
- project_10245 - Free and universal breakfast clubs - national rollout evaluation · Department for Education · £1,475,777
- Consultancy for Kent Housing Group · Ashford Borough Council · £67,688
- Trust Policy Interventions Research · Department for Culture, Media and Sport · £80,981
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.