Construction Embedded rock ramp fish pash near Red Rock
key details
| Value | £57,913 |
|---|---|
| Status | complete |
| Category (CPV) | 45240000 |
| Region | North West |
| Deadline | 7 Dec 2020 |
| Contract start | 7 Jan 2021 |
| Contract end | 30 Sept 2021 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-3e56ab93-4bc6-494f-86ee-5fcb554f9b83 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Bailey Contracts Ltd | £33,900 | 16 Feb 2021 | active |
description
The Opening Up the River Douglas programme (OUR Douglas), funded by the European Regional Development Fund (ERDF), aims to specifically address and improve fish passage in the Douglas Catchment, creating a fish easement which allows for the passage of all fish species at all times. As such the project is advertising this contract opportunity for the detailed design and construction of a embedded rock ramp fish pass at the weir near Red Rock.
documents
- https://ribbletrust.org.uk/contract-opportunities/our-douglas-contract-opportunity-red-rock-weir/ , biddingDocuments
- https://www.contractsfinder.service.gov.uk/Notice/6f326345-6bca-4aa5-979a-8bc033b4f447 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 10 Feb 2022 | Award update (awardUpdate) | · | 44f4b498-2c79-475b-a9f0-998b7a978b7f-509157 |
more from RIBBLE CATCHMENT CONSERVATION TRUST LIMITED
- Design and Construction Weir Removal at Cobbs Clough Weir · £30,000 · 5 Dec 2022
- Detailed Design and Construction of Rock-Ramp Fish Pass at Gathurst Weir on the River Douglas · £87,738 · 10 Feb 2022
- Design and Build Pottery Terrace Rock Ramp Fish Easement · £65,293 · 20 May 2021
- Lomeshay River Restoration · £500,000 · 4 Nov 2020
- Design and Construction Rock Ramp Fish Pass at Worthington Lakes · £81,010 · 15 Oct 2020
- Design and Construction Rock Ramp Fish Pass Upstream Pincroft Works · £43,140 · 15 Oct 2020
- Embedded rock ramp fish pass at the weir downstream Pincroft weir · £63,000 · 19 May 2020
- Loose fill rock ramp fish pass at the weir downstream of Grimeford Lane · £64,000 · 19 May 2020
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Open Brook Courses and Trash Screens Maintenance · Manchester City Council · £1,400,000
- South Hams Dredging · South Hams District Council · £99,999
- Invitation to Tender For Relining of Pond at Kent & Sussex Crematorium · TMT Procurement Partnership
- Maintenance Work On Sterte Channel · Bournemouth Christchurch and Poole Council · £493,387
- Extension to Coastal Engineering Minor Works Framework Agreement: Southern Coastal Group and SCOPAC (Southern England) · Portsmouth City Council
- Royal Navy Submarine Museum- Waterbus Jetty Works · National Museum of the Royal Navy · £100,000
- Beneficial Use of Dredged Sediment - Boiler Marsh, Lymington · The Crown Estate · £503,860
- New water supply, Lower Valley Farm (BNG site), Fulbourn Cambridgeshire · Cambridgeshire County Council · £30,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.