gvtcx

Rushmire Hill Geotechnical Remediation and Standish Multi-User Path

Gloucestershire County Council Published 26 Sept 2024 Contracts Finder

key details

Statuscomplete
Category (CPV) 45000000
Deadline31 Oct 2024
Contract start6 Jan 2025
Contract end30 May 2025
Procedureopen
SME suitableYes
OCIDocds-b5fd17-3d624723-6298-4f36-905f-61f8547a6226

Award

SupplierValueDateStatus
Montel Civil Engineering Ltd £1,741,800 17 Dec 2024 active

description

This advert is intended to notify potential suppliers of the combined tender including both the Rushmire Hill Geotechnical remediation and the Standish Multi-User Path works. These two pieces of work have been packaged as a single tender.

Rushmire Hill Geotechnical Remediation

Rushmire Hill is in South Gloucestershire, near Wotton-under-Edge, approximately 1.2 km south of Cotswold Edge Golf Course. The works are required to stabilise the B4058 carriageway, which has historically suffered deterioration from ground movement. Remediation works will include sheet piling along the GCC owned verge, verge and carriageway reconstruction. Site clearance will also be required to facilitate the piling works.

Summary of Construction Phase key deliverables are as follows:

Site clearance including tree clearance over approx. 255m, 3.5m width.

Sheet piling installation along an approx. 255m length of verge.

Partial carriageway reconstruction of the northbound carriageway over 280m.

Carriageway resurfacing over approx. 300m

Ground investigation including the installation of 3 no. inclinometers and 1 no. slotted standpipe in the carriageway

Traffic Management during the construction works.

Maintain residents' access during the construction works.

Standish Multi User Path

The works are located between the Horsemarling Lane roundabout and Blackbridge access track to the south of Standish, Gloucestershire. This scheme is part of a wider strategic scheme to boost active travel provision within the county, through the creation of the Gloucestershire Cycle Spine and includes a section of bridle way.

Summary of Construction Phase key deliverables are as follows:

Construction of 400m of 3m wide new shared use path and bridal way

150m of carriageway realignment and works to splinter island

Streetlighting column installation and relocation. Columns will be supplied by GCC.

Utility diversion works (pre-arranged by GCC for Principal Contractor to liaise/accommodate).

Drainage works that tie-in to existing systems and includes ditch and attenuation pond construction.

Traffic Management during the construction works.

Maintain residents' access during the construction works

Gloucestershire County Council are seeking a Principal Contractor to deliver the construction phase of this project.

A summary of the outline programme for the combined packages of works is shown below:

Tender period: 26th Sep - 31st Oct 2024

Award: Monday 25th November 2024

Anticipated Works Start Date: Monday 6th January 2025

Completion: Friday 30th May 2025

Overall Duration: 22 weeks

Indicative Value: (£2.2M + £0.44M VAT) = £2.64M

The proposed procurement route will be a single stage (Open Procedure) using the NEC4 ECC form of Contract, Option A Priced Contract with Activity Schedule.

Full details will be available in the tender pack advertised on Procontract Thursday 26th September 2024.

https://procontract.due-north.com/Advert?advertId=e79b7d6e-ad6f-ef11-812f-005056b64

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
26 Sept 2024 Tender (tender) · b61e0676-d175-4672-a74d-8622515cf4a6-788945
14 Feb 2025 Award (award) · 505d28bf-bc67-4b06-b1dc-16ab49fcaf9f-826400

more from Gloucestershire County Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.