Project Management Resourcing Covering Clinical Imaging Capital Projects

Guy's and St Thomas' NHS Foundation Trust Published 23 Jun 2023 Contracts Finder
The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£114,900
Statuscomplete
Category (CPV) 72224000
RegionLondon
Deadline22 Dec 2022
Contract start15 May 2023
Contract end15 Nov 2023
Procedureselective
SME suitableYes
OCIDocds-b5fd17-35dad764-d7d0-4928-8012-30721fd9f856

Award

SupplierValueDateStatus
Provelio Ltd £110,000 21 Jun 2023 active

description

The Trust require a Single Consultant Team or Contractor to provide a Team of individuals for Professional Services Roles outlined below.

The appointed Consultants will be embedded in the Project Team and working alongside Essentia Staff, and will report into the Programme Manager, Senior Project Manager for the MIEG Capital Programme. As well as working alongside other permanently employed staff such as but not limited to Project Managers, Assistant Project Managers, Project Support Officers, and other internal and external project stakeholders.

Project Manager to work on the following projects during RIBA Work Stages: -

  • Replacement of IR Room 15 in St Thomas' Hospital - Progress through RIBA Work Stages 0-2 for OBC by end of November 2023, if contract extended then progress to RIBA Stage 3-4 for FBC by end of April 2024.
  • Replacement of E-Cam Gamma Camera in St Thomas' Hospital - Progress through RIBA Work Stages 0-2 for OBC by end of September 2023, if contract extended then progress to RIBA Stage 3-4 for FBC by end of March 2024.
  • Replacement of ED X-Ray Room 3, 1st Floor Lambeth Wing, St Thomas' Hospital - Progress through RIBA Work Stages 4-6 by end of August 2023, including construction, witnessing, testing and commissioning and handover, and project close-out.
  • Replacement of Guys CT, 3rd Floor Tower, Guys Hospital - Progress through RIBA Work Stages 4-5 by end of October 2023, including construction, witnessing, testing and commissioning and handover, and project close-out.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
23 Jun 2023 Award (award) · 455344e8-7610-41ac-944c-99e72de7a53c-656177

more from Guy's and St Thomas' NHS Foundation Trust

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.