Swindon Borough Council Published 10 Oct 2022 Find a Tender

key details

Value£14,400,000
Statusactive
Category (CPV) 45212212 +9 more
RegionSouth West
Deadline9 Nov 2022
Procedureselective
OCIDocds-h6vhtk-03745a

description

Swindon Borough Council, wishes to submit to tender the requirements for the provision of works relating to the phased restoration and enhancement of the Grade II* Health Hydro. The works fall into two Phases. Phase 1 is fully funded. Funding for Phase 2 is dependent on the Levelling Up Fund round 2 bid, which was submitted in August 2022.

The Phase 1 works include:

Repairs and conservation works to roofs and external façades
Replacement of mechanical electrical and plumbing plant and systems for the phase 1 areas
Creation of new building areas to house new MEP plant
Installation of new MEP plant and systems for Phase 1 areas
Repairs and restoration works to the large swimming pool and its hall
Reconfiguration and enhancement to the changing facilities
Strip out of modern interventions and redundant MEP plant and systems within the phase 1 areas notably, in the former Washing Baths Hall
Reconfiguration of the former Washing Baths Hall to enable new activity space and access through to the changing and wet-side areas
Reconfiguration and restoration works to the Milton Road entrance
Improved access and circulation

The Phase 1 scheme will provide the enabling platform for the further and complete restoration and enhancement of the Health Hydro to be realised.

The Phase 2 scheme includes:

Reconfiguration of the former dispensary and consulting / practitioner rooms on the ground floor to create a new Community Health and Wellbeing Hub
Reconfiguration and restoration works to the Faringdon Road entrance
Restoration and enhancements to the Turkish Baths and Spa
Environmental improvements to the main pool hall, focusing on roof insulation and re-glazing

The initial contract term will be for 16 months for phase 1 with an option to extend for a further 12 months for phase 2 with a potential total contract term of 28 months as stated in the ITT documents. Estimated contract spend for phase 1 is £5.3m and £9.1m for phase 2.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
10 Oct 2022 Contract notice (F02) Earlier regulations 028402-2022
10 Oct 2022 Tender (tender) · 9a138c75-e8bc-4044-a9a9-dd38092b524c-579436

more from Swindon Borough Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Find a Tender. Contact details for named individuals are not reproduced on this site.