Thames Tideway Tunnel - C405 Main Works West - Permanent Formwork Decking
key details
| Status | complete |
|---|---|
| Category (CPV) | 44114250 +3 more |
| Region | London |
| Deadline | 13 Nov 2020 |
| Contract start | 1 Dec 2020 |
| Contract end | 6 May 2021 |
| SME suitable | No |
| OCID | ocds-b5fd17-32e40f0f-ba3c-4ee9-b580-4295713335e5 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| not named | £43,000 | 1 Dec 2020 | active |
description
The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.
The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.
The Project comprises:
- a.tunnels:
- i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
- ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
- b.Worksites:
- i.five main tunnel Worksites (drive and/or reception sites)
- ii.16 CSO Worksites
- iii.two System modification Worksites Thames Tideway Tunnel
- iv.works at Beckton Sewage Treatment works.
Section 4: Scope of Works
Part 1)
Scope of Supply Attenuation Tank:-
BMB JV require fabrication and supply of permanent formwork for an Attenuation Tank at Hammersmith site. Panels shall be made to the geometry displayed in the drawings provided for the Attenuation Tank. All panels are to be laminated as the soffit will be submerged by BMB JV systematically.
Panels shall be delivered to site labelled in-order to allow BMB JV to install the panels in the correct sequence.
Supply of all ancillary items such as grout check and joint sealing tapes should be detailed and included in the supply.
All supporting documentation for a material compliance report should be provided prior to order delivery.
No openings are required as BMB JV will post cut on site.
Attenuation Tank Building Drawings 3320-AAJVX-HAMPS-540-SZ-DR-000040
3320-AAJVX-HAMPS-540-SZ-DR-000041
Part 2)
Hammersmith Shaft Scope of Supply: -
BMB JV require fabrication and supply of permanent formwork for a drop shaft at Hammersmith site. The supplier is to conduct a design check on the panels proposed for permanent and temporary loadings and spans for the Hammersmith Shaft.
Supply of all ancillary items such as grout check and joint sealing tapes should be detailed and included in the supply.
Panels shall be delivered to site labelled in-order to allow BMB JV to install the panels in the correct sequence.
Supplier will produce manufacturing drawings for panel layout for BMB's approval. All documentation to be supplied for panel layout to be checked by BMB temporary works department before commencement
Additional information: BMB-JV Tideway West, Hammersmith Pumping Station, Distillery Road, Hammersmith, W6 9AD
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 12 Mar 2021 | Award (award) | · | 45069d1f-46f3-4df9-834e-56e40917a134-418177 |
more from BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)
- Thames Tideway Tunnel - C405 Main Works West - Carnwath Road Pit Bottom Steel Alterations · £1 · 5 Jul 2021
- Thames Tideway Tunnel - C405 Main Works West - Intertidal Terrace · £1 · 5 Jul 2021
- Thames Tideway Tunnel - C405 Main Works West - Pipe Jacking works for Syphon Main ACTST · £500,000 · 9 Apr 2021
- Thames Tideway Tunnel - C405 Main Works West - Hammersmith Security Gates & Fencing · £1 · 17 Feb 2021
- Thames Tideway Tunnel - C405 Main Works West - Main Tunnel Steel Connection Shutters · 5 Feb 2021
- Thames Tideway Tunnel - C405 Main Works West - Bulkheads (Acton) · £1 · 8 Jan 2021
- Thames Tideway Tunnel - C405 Main Works West - Hammersmith Connection Culvert Bulkhead · £1 · 21 Oct 2020
- Thames Tideway Tunnel - C405 Main Works West - Putney Tunnel Connection Shutter · 21 Oct 2020
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- ST0581 Broughton Astley Deck Replacement Scheme - Manufacture of Precast Concrete Deck Slab Units · Leicestershire County Council
- Substructure, below ground design, water supply and connection of services for a new Public WC · Trowbridge Town Council · £25,000
- BE24054 - Test Blocks · UK SHARED BUSINESS SERVICES LIMITED · £81,769
- RC Pad · The Queen Elizabeth Hospital King's Lynn Nhs Foundation Trust · £18,226
- COV - VLR Slab Track TP2 · Coventry City Council · £59,158
- Concrete Pad and Path for Modular Building · The Queen Elizabeth Hospital King's Lynn Nhs Foundation Trust · £10,559
- DPS-01C/MM/101- HMP Cardiff G-Wing Compound · Ministry of Justice · £77,742
- For the UKAEA Culham Installation of Middleway Slab Duct Covers · United Kingdom Atomic Energy Authority · £1,630,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.