NNL are currently contracted to carry out a series of trials to measure radiolytic gas generation.

Because these measurements are to be made using irradiated material there are two significant constraints:

  • The quantity of material (predominantly a powder) used in each test must be minimised.
  • The samples and vessels must remain within a hot cell facility (see Appendix for details), therefore:
  • oSample lines between the text vessels and the measurement system located outside the hot cell will be long (~6-10 m).
  • oItems in the hot cell will receive significant radiation doses and must be suitably radiation hardened.
  • oAll operations on equipment located in the hot cell (setup, operation, maintenance and dismantle) must be carried out remotely using master slave manipulators (see Appendix for examples).
  • oAmbient temperature may vary in the range 5°C - 40°C during the year.

NNL has developed a preliminary concept for undertaking the required measurements, show in Figure 1 :

Figure 1 Initial Sampling Concept

Some relevant characteristics of the proposed system are:

  • Individual tests will be conducted on a few grams of irradiated material in high integrity vessels with a total volume of ~ 3 cm3 and a free volume of ~ 2 cm3.
  • Connecting pipework to be narrow-bore, high pressure piping (nominally 1.6 mm, 1/16" bore)
  • The gas generated, in the test and whose composition needs to be measured, will depend on the test material and may be composed of either:
  • oHydrogen and sub-stochiometric quantity of oxygen (the degree of sub-stoichiometry is currently unknown);
  • oRoughly equal amounts of hydrogen, carbon dioxide, carbon monoxide and methane, with trace amounts of higher hydrocarbons.
  • Small quantities of Kr and He may be released from the test materials as a result of radioactive decay, and their presence would need to be accounted for.
  • The reference sampling process would involve:
  • oEvacuating the manifold and isolating it.
  • oOpening the valve for designated test vessel valve to equalize pressure with manifold following which the valve would be closed to leave a gas sample of around 50µL in the manifold.
  • oSweep the sample using a carrier gas to it to the measurement instrument.
  • An equilibrium is expected to form which will limit the overall pressure generated. It can be assumed that the experiment will be terminated if the pressure exceeds a value which is expected to be less than 50 BarG.
  • Tests will be conducted for a number of source materials and test conditions, leading to between 20 and 30 simultaneous tests.

Scoping calculations suggests that

  • gas will be generated at a rate of ~ 10-9 moles per day.
  • the pressure rise will be ~1.5 x 10-5 Bar.d-1 and
  • the concentration of each species will increase by
  • o~90 ppm per week of hydrogen, or
  • o~20 ppm per week each of hydrogen, methane etc.
  • The tests may last between 3 and 12 months

Additional information: NNL are currently contracted to carry out a series of trials to measure radiolytic gas generation from materials associated with spent nuclear fuel. One of the specific technical objectives is to determine the change in gas composition with time.

Following the supplier meeting NNL intends to hold a series of 1:1 meetings with individual suppliers, which will provide an opportunity to discuss possible measurement solutions in greater detail.

Anyone who wishes to have such a meeting should submit a brief overview of their recommended measurement approach, which may differ for the concept provided above if an alternative measurement system is able to provide the required measurement capability. The overview must demonstrate that the measurement system has a proven track record and can be deployed for undertaking measurements in a hot cell facility. Provided that NNL considers that the proposed scheme is viable, and the measurement system is reliable, a detailed meeting will be agreed. The total number of 1:1 meetings will be capped at ten. In the event that more than 10 viable approaches are suggested then meeting slots will be allocated on a first come first served basis.

The dates and time slots for 1:1's are as follows:

Thursday 20th August Friday 21st August

09:00 - 09:45

10:00 - 10:45

11:00 - 11:45

13:00 - 13:45

14:00 - 14:45

When providing your response, please indicate which date and time would be most convenient and we will try to accommodate.

Please be aware that Matt McClure, the Procurement & CTM is on leave 31/07/2020 until 10/08/2020. Dial in details will be sent and any questions will be answered on return.

NNL considers that the measurement of gas composition at intervals during the test is challenging and that the gas sampling and measurement techniques required are outside of its area of expertise. NNL is therefore requesting assistance from suppliers to help identify credible means of making the proposed measurements in order to enable NNL to define a specification for a subsequent open procurement process to provide a suitable measurement system.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
3 Aug 2020 Planning (planning) · efac1fa2-f81d-4ef3-950e-5017ae0cdbeb-373734

more from Sellafield

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.